1 / 6

Nodal MIS Portal Project

Nodal MIS Portal Project. MIS Functions to Support EDS 3, Release 5 September 11, 2007. Status of Key Activities to Meet SCED Objectives as reported to TPTF 08/28/07. MIS Status for EDS 3, Release 5 as of 09/10/07. Working to deliver SCED reports as prioritized by TPTF.

trivers
Download Presentation

Nodal MIS Portal Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Nodal MIS Portal Project MIS Functions to Support EDS 3, Release 5 September 11, 2007

  2. Status of Key Activities to Meet SCED Objectivesas reported to TPTF 08/28/07

  3. MIS Status for EDS 3, Release 5as of 09/10/07

  4. Working to deliver SCED reports as prioritized by TPTF • Working with MMS Vendor to implement SCED outputs through MMS UI • Developing requirements for EMS reports by working with ERCOT business • SCED Outputs • LMPs for each Resource Node (1) • Settlement Point Prices at Hub and Load Zone (2) • SCED Shadow Prices (3) • Binding transmission constraints (4) • LMP Contour Map • EMS Outputs • 15 min average of Loads on Electrical Buses (5) • Status of breakers and switches • Transmission flows and voltages from SE • Individual transmission Load on Electrical Buses • Sum of Load on each Electrical Bus in each Load Zone • Total Load on Electrical Buses in the ERCOT System • Sum of ERCOT generation • All voltage schedules • (Priority as defined by TPTF) • Differences in MMS design and Market Participant expectations could lead to delay in implementation of LMP Contour Map

  5. Why the potential delay in reporting? • Original plan for delivery of Reports & Extracts was a distributed responsibility shared across multiple Nodal projects • TPTF update presented by Pat Harris on 02/06/07 • “Application systems own the content – requirements, generation, responsibility for accuracy” • “Application systems sign off on its accuracy” • “Data owners from each Nodal Project Team generate requirements to define data products originating from their systems” • Issue: no single ownership - application systems focused on core application functionality; reports/extracts requirements inconsistent across projects • Revised plan - single, focused responsibility driven by MIS project & PMO • Coordinated effort will still require MP, Business, and Nodal application project involvement; however single point of management can drive priorities and ensure EDS synchronization

  6. Q & A

More Related