1 / 25

Strategic Sourcing

Strategic Sourcing. What is Strategic Sourcing. Applicability of Strategic sourcing. Process. Sourcing lever - Examples. Leverage volume Buying solutions not products Third party solution provider Direct purchase from manufacturer Optimization of specifications Long term contracts

tybalt
Download Presentation

Strategic Sourcing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Strategic Sourcing

  2. What is Strategic Sourcing

  3. Applicability of Strategic sourcing

  4. Process

  5. Sourcing lever - Examples • Leverage volume • Buying solutions not products • Third party solution provider • Direct purchase from manufacturer • Optimization of specifications • Long term contracts • Supplier managed inventory • Total cost of ownership • Life cycle costing • Conversion route • Joint improvement initiatives • Reverse auctions • Free delivery at site • Leveraging payment terms • Diversifying risks

  6. Supplier Value Management Approach (SVM) – Focus Area • Value-creating partnerships (win-win) between customer & vendor • Optimizing costs and resources in the entire value chain • Understand each others requirement & eliminate inefficiency, assumptions in the chain & align the supplier to the end customer’s requirement • Establish communication channels at all levels to leverage knowledge and resources for mutual benefit • Create a platform for continuous improvement • Thorough understanding of entire supply chain can be developed on: • Cost base of Supplier • Usage Cost: Product specification, design, new product development, cycle time reduction etc. • Impact of technology • Quality • Bottlenecks • Future requirements of Buyer & Supplier • Benefits: • Overall cost base reduction at Buyer and Suppliers end • Better understanding of each other requirements • A joint working atmosphere

  7. Case Study – Hired Material Handling Equipments • Background: • Spend: Rs. 400 – 500 Lacs • GHCL - SA plant handles approx. 10000 MT of bulk material – daily. Material handling includes • Feeding of RM in SA plant and its internal movement • Proper storage of excess material to ensure optimum utilization of available storage space • Loading of vehicles to shift bulk material like ash, undersize Limestone, etc. out of plant • Part of bulk material is handled using mechanized system (Truck tipplers, conveyors, etc.) and part is handled using hired equipments viz. loader, dumper, TC, dozer, excavator, etc. • Challenges: • In spite of having full fledged mechanized system to cater for 100% RM requirement of plant, Sizable amount of material was handled using hired equipments due to variety of reasons viz. • Irregular receipt of RM during the year as well as during the day • Requirement to store large volume of RM for usage during monsoons, festival, etc. due to scarce supply • Spend followed uniformly upward trend due to dependence on diesel prices, manpower cost equipment capital and maintenance cost

  8. Case Study – Hired Material Handling Equipments • Methodology adopted: • Formulation of cross functional team • Graphical depiction of MH activity: Multiple re-handling observed due to lack of online storage facilities, scope for improvement in mechanization, scope for contract re-engineering type which was hourly based, etc. • External analysis – Study of similar industries practices: Each unit scrutinized had their unique contracts for handling bulk material. As is implementation in our system was not feasible • Hypothesis compiled for further consideration, which included – • Conversion of hourly based payment contracts to MT based contracts, • clubbing of activities • contract consolidation to improve equipment utilization, etc. • create online storage facility

  9. Case Study – Hired Material Handling Equipments • Conclusion / Outcome: • Indirect tonnage measuring method adopted for tonnage based contract. Approx. 87% of handling activities are being carried out on tonnage basis which was about 43% earlier. Benefits - reduction in requirement of continuous supervision, simplified operations and increased accountability of contractor • Activities were consolidated in Sizer operation for better equipment utilization and hence derive cost benefits • Contracts renegotiated based on alternate quotations received from experienced outside contractors. Though original contractors were not changed, to avoid local disturbance • Proposals for creation of Online storage facilities (storage on top of conveying system) are generated & may be implemented post budgetary approvals

  10. Case study - Paints • Total painting area - 8.50 Lacs Sq. M (approx) • Current Scenario: • PU base system with Guarantee: 1.5 yrs (max) based on corrosion audit conducted in yr 2003-04 by CECRI • 25 paint schemes were applicable across the plant • Non-availability of Quality Vendors for polyurethane based paint application • Hypothesis: • Adopting Epoxy based paint system instead of Polyurethane • Reducing no of schemes of paint application across the Plant • Reduction of Life Cycle cost by increasing guarantee period • Synopsis: • Corrosion Audit was conducted AkzoNobel & report submitted with latest painting solutions • Trial order to M/s Akzo Nobel for highly corrosive area with Epoxy base system with guarantee of 5 yrs • Division total plant area in two parts based on corrosiveness, • Highly  corrosive ( 1.5 L Sq. M area) • Moderate corrosive (7 L Sq. M area) • Corrosion audit conducted by renowned vendors to design their own painting schemes with min. 3/5 yrs guaranteed life • 8 schemes were finalized post technical evaluation

  11. Case study - Paints • M/s Kansai Nerolac was finalized for long term contract based on life cycle cost instead of per liter cost of paint • Benefits: • Total Ownership of Paint Application was transferred to Vendor • Reduction in Inventory level • Savings in Application Cost & Time

  12. Case Study – Bearings • Scenario: • Annual Spend: Rs 110 lacs(approx) • No of Vendors: 4 Nos (FAG,SKF, NTN, Timken) • Annual Rate Contract with Authorised Dealer of FAG & SKF • Challenges: • Transaction with high number of Vendors • High Lead time in procurement • Price List based items (Less Discount was offered by Authorised Dealers) • Higher Inventory level was maintained for satisfying frequent Maintenance requirement • Remedial Actions Taken • Direct OEMs (SKF& FAG) invited to study our consumption pattern and submit offer for long term contract. • Contract was finalized with SKF, with VMI at plant • Benefits • Discount Structure was revised from 25% to 27% on list price with 5% TOD • VMI was introduced without any additional cost. • Better Discount and T&Cs were extended to other units of GHCL (Vapi & Madurai)

  13. Case studies

  14. Challenges • Gathering information during External Analysis – due to unwillingness of Industry to share sourcing information • Inherent resistance to change • Implementing changes that are locally sensitive • Cost & time involved in experimentation • Confidence building exercise within team • Clash of priorities – Development exercise vs Production

  15. Projects Procurement

  16. Nature of Projects in SA division during past few years

  17. Highlights of past few years • Average project spend per annum Rs. 5000 Lacs • Standardised project cost estimation format to incorporate indirect expenses for accurate project budgeting • Continuous review of project progress, project cost and taking corrective measures to minimise delays / cost overruns • Established practice of finalising high value equipments in competitive environment, as against practice of dealing with single vendors. Hence deriving sizable cost benefits • Introduction of alternate vendors has resulted in savings • Establishing practice of deriving breakdown costing in case of technical preference for procurement of technological equipments from single vendors • Incorporation of Project MIS report in SAP with budget cap • Usage of SHIS for duty benefits

  18. Process flow

  19. Process flow

  20. Challenges & Takeaways from major projects

  21. Challenges & Takeaways from major projects

  22. Challenges & Takeaways from major projects

  23. Challenges & Takeaways from major projects

  24. Challenges & Takeaways from major projects

  25. Thanks

More Related