The Bridge Fire – Lake County MP 282 – Turnpike over CR 561 Paul Wai Director of Highway Operations

The Bridge Fire – Lake County MP 282 – Turnpike over CR 561 Paul Wai Director of Highway Operations. Accident and Incident Response. Accident and Fire under Turnpike Northbound Bridge Lake County Fire and Rescue CR 561 Closed FHP Troop K Turnpike Closed

tyson
Download Presentation

The Bridge Fire – Lake County MP 282 – Turnpike over CR 561 Paul Wai Director of Highway Operations

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Bridge Fire – Lake County MP 282 – Turnpike over CR 561 Paul Wai Director of Highway Operations

  2. Accident and Incident Response • Accident and Fire under Turnpike Northbound Bridge • Lake County Fire and Rescue • CR 561 Closed • FHP Troop K • Turnpike Closed • Turnpike traffic detoured off system

  3. The Event +24 Hours

  4. Structural Assessment • Span 2 Replacement • Rehabilitation for substructure • Minor Repairs adjacent Spans

  5. Project Mission & Organization • Diversion for Turnpike NB • Bridge Reconstruction • Traffic Management • Public Outreach • 24/7 Operation Orlando Sentinel December 16, 2009

  6. Coordination • Team Turnpike • Maintenance • Public Information • Traffic Operations • Construction • Production • Materials • Toll Operations • FHP • FDOT Districts 2, 3, 5 and Central Office • OOCEA • Lake County

  7. Emergency Contracts • Cone & Graham • Bridge Reconstruction • $831K Open to Traffic by 3pm December 31st • $150K Bonus for opening by 12am December 24th • Lane Construction Corporation • Roadway Diversion and Maintenance of Traffic • $774K to open diversion by 8am December 16th • $50K Bonus for restoring normal traffic flow by 5am December 24th • The Car Store • Support Incident Management • $50K for two prepositioned wreckers

  8. Bridge Reconstruction • Built in 1964 • Standard Drawings 1962 • Three Span • Beams • Type II Girders(7) – 46 FT • 8500 PSI (Req. 5000 PSI) • Deck • 7” Deck • Concrete Parapet and Aluminum Handrail • 6500 PSI (Req. 4000 PSI)

  9. Traffic Management • TMC • Cameras • Vehicle Detection Devices • DMS Boards • Portable Message Boards • Highway Advisory Radios • CB Radio Alert System • Hourly Reports • Travel Speeds • Volume • Toll Suspensions • Traffic Queue Protection

  10. Travel and Traffic Information • News Conference and Releases • Internet • Email • Web Blogs • floridasturnpike.com • FL511.com • Posters • Toll Plazas • Service Plazas and Fuel Stations • Rest Areas & Welcome Centers • Customer Calls

  11. Mission Timeline North Bound Traffic Diversion Open Beams Set Span 2 Demolition Complete Deck Poured Barrier Walls Poured Northbound Diversion Removed Accident Occurred Bridge Ready for Traffic

  12. Mission Success • Safety First • Event +24 Hours Critical • Serve our Customers • Travel & Traffic Information • Right People • Can Do Attitude • Motivated • TEAMWORK!

  13. Mission Heroes • Bridge Reconstruction: Randy Cropp, Cone and Graham • CEI Project Manager: Walt Lange, Cardno TBE Group • Diversion & MOT: Tommy Sample, Lane Construction • TEAM Turnpike

  14. Thank you Paul Wai (954) 934-1247 paul.wai@dot.state.fl.us Jose Quintana (954) 934-1209 jose.quintana@dot.state.fl.us

  15. Tolling & TransitA Public-Public Partnership Miami Dade Expressway Authority “Moving Miami-Dade” Alfred Lurigados, P.E. Director of Engineering MDX