The Bridge Fire – Lake County MP 282 – Turnpike over CR 561 Paul Wai Director of Highway Operations. Accident and Incident Response. Accident and Fire under Turnpike Northbound Bridge Lake County Fire and Rescue CR 561 Closed FHP Troop K Turnpike Closed
E N D
The Bridge Fire – Lake County MP 282 – Turnpike over CR 561 Paul Wai Director of Highway Operations
Accident and Incident Response • Accident and Fire under Turnpike Northbound Bridge • Lake County Fire and Rescue • CR 561 Closed • FHP Troop K • Turnpike Closed • Turnpike traffic detoured off system
Structural Assessment • Span 2 Replacement • Rehabilitation for substructure • Minor Repairs adjacent Spans
Project Mission & Organization • Diversion for Turnpike NB • Bridge Reconstruction • Traffic Management • Public Outreach • 24/7 Operation Orlando Sentinel December 16, 2009
Coordination • Team Turnpike • Maintenance • Public Information • Traffic Operations • Construction • Production • Materials • Toll Operations • FHP • FDOT Districts 2, 3, 5 and Central Office • OOCEA • Lake County
Emergency Contracts • Cone & Graham • Bridge Reconstruction • $831K Open to Traffic by 3pm December 31st • $150K Bonus for opening by 12am December 24th • Lane Construction Corporation • Roadway Diversion and Maintenance of Traffic • $774K to open diversion by 8am December 16th • $50K Bonus for restoring normal traffic flow by 5am December 24th • The Car Store • Support Incident Management • $50K for two prepositioned wreckers
Bridge Reconstruction • Built in 1964 • Standard Drawings 1962 • Three Span • Beams • Type II Girders(7) – 46 FT • 8500 PSI (Req. 5000 PSI) • Deck • 7” Deck • Concrete Parapet and Aluminum Handrail • 6500 PSI (Req. 4000 PSI)
Traffic Management • TMC • Cameras • Vehicle Detection Devices • DMS Boards • Portable Message Boards • Highway Advisory Radios • CB Radio Alert System • Hourly Reports • Travel Speeds • Volume • Toll Suspensions • Traffic Queue Protection
Travel and Traffic Information • News Conference and Releases • Internet • Email • Web Blogs • floridasturnpike.com • FL511.com • Posters • Toll Plazas • Service Plazas and Fuel Stations • Rest Areas & Welcome Centers • Customer Calls
Mission Timeline North Bound Traffic Diversion Open Beams Set Span 2 Demolition Complete Deck Poured Barrier Walls Poured Northbound Diversion Removed Accident Occurred Bridge Ready for Traffic
Mission Success • Safety First • Event +24 Hours Critical • Serve our Customers • Travel & Traffic Information • Right People • Can Do Attitude • Motivated • TEAMWORK!
Mission Heroes • Bridge Reconstruction: Randy Cropp, Cone and Graham • CEI Project Manager: Walt Lange, Cardno TBE Group • Diversion & MOT: Tommy Sample, Lane Construction • TEAM Turnpike
Thank you Paul Wai (954) 934-1247 paul.wai@dot.state.fl.us Jose Quintana (954) 934-1209 jose.quintana@dot.state.fl.us