APRP Meeting MICE UK work packages Costs and schedules. Organisation and monitoring Schedule summaries Cost summaries. Andy Nichols, STFC, 15/8/11. Organisation and Monitoring. A MICE UK Project Manager, Alan Grant of DL, was appointed earlier this year
E N D
APRP MeetingMICE UK work packagesCosts and schedules • Organisation and monitoring • Schedule summaries • Cost summaries Andy Nichols, STFC, 15/8/11
Organisation and Monitoring • A MICE UK Project Manager, Alan Grant of DL, was appointed earlier this year • He is accountable for delivery of UK work-packages – See Paul’s slides • Chairs weekly Cost and Schedule meeting (among many other things) • Mary Elizabeth Shewry is secretary and organiser of raw cost data • At that meeting, each WP manager: • Compares and explains planned and actual spend • Describes progress against milestones • Provides a brief technical update
Overall Project Milestone table
Optimal MICE Top-level schedule • Mapped onto the International Project requirements • Steps V & VI are critically subject to international deliverables
Table of resources, profiled to achieve optimal project schedule
By delaying the implementation of the UK project, it is possible to achieve a • flat profile for four years • But: • This leads to a higher overall cost • Is not necessarily acceptable to the international project • Would have a negative effect on staff/skill retention and motivation
WP4 – Focus Coil Module Note: schedule details shown are for purchase of module 3 only