1 / 22

N.A. ZUBERI MANAGING DIRECTOR PRIVATE POWER & INFRASTRUCTURE BOARD October 22, 2011

INTERNATIONAL COAL CONFERENCE. “CONVERSION OF EXISTING THERMAL POWER PLANTS TO COAL”. N.A. ZUBERI MANAGING DIRECTOR PRIVATE POWER & INFRASTRUCTURE BOARD October 22, 2011. C O N T E N T S. Overview of Pakistan Power Sector Power Plants for Coal Conversion

urbain
Download Presentation

N.A. ZUBERI MANAGING DIRECTOR PRIVATE POWER & INFRASTRUCTURE BOARD October 22, 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INTERNATIONAL COAL CONFERENCE “CONVERSION OF EXISTING THERMAL POWER PLANTS TO COAL” N.A. ZUBERI MANAGING DIRECTOR PRIVATE POWER & INFRASTRUCTURE BOARD October 22, 2011

  2. C O N T E N T S • Overview of Pakistan Power Sector • Power Plants for Coal Conversion • Issues on Conversion of Power Plants to Coal • Implementation Mechanism for Converting Plants to Coal • Key Features of Mechanism for Converting GENCOs/IPPs to Coal • Conclusion

  3. PAKISTAN POWER SECTOR TOTAL INSTALLED CAPACITY MW % Public Sector WAPDA/SHYDO/ NA/AJK 11,603 52 PAEC 4622 Sub-Total 12,065 54 Private Sector IPPs 8,508 38 KESC 1,756 8 Sub-Total 10,26446 G. Total 22,329100 Public Sector Thermal 4,900 MW Nuclear 462 MW Public Sector Hydel 6,703 MW IPPs 10,039 MW

  4. POWER GENERATIOINTECHNOLOGIES • STEAM TURBINE POWER PLANTS • GAS TURBINE POWER PLANTS • COMBINED CYCLE POWER PLANTS • RECIPROCATION ENGINES

  5. PAKISTAN POWER SECTOR – TRANSMISSION SYSTEM MARDAN WARSAK (240) TARBELA (3408) GAZI BAROTHA I.S.P.R (1450) NEW RAWAT BURHAN MANGLA BANNU (1000) CHEP DAUDKHEL (184) SABA GAKHAR GATTI SAHOWALA CHASNUPP ROUSCH K.S.KAKU (310) RAVI BUND RD: (107) JAPAN N.ABAD (355) (120) KEL KAPCO (1348) YOUSAF WALA HCPC AES (126) VEHARI UCH (195) N.G.P.S M.GARH (548) M.GARH GUDDU (1350) (1655) GUDDU 500 kV Grid Station 220 kV Grid Station 500/220 kV Grid Station Hydel Power Station Thermal Power Station IPPs at 220, 500 kV IPPs at 132 kV 500 kV T/LINE 220 kV T/LINE LIBERTY (212) DADU HALARD (1200) KOTRI (174) LAKHRA (150) JAMSHORO HUBCO JAMSHORO (850) G.AHMAD KDA-33 (KESC)

  6. PAKISTAN POWER SECTOR FUEL MIX (2009-10)

  7. EXISTING POWER SECTOR SITUATION • 60% power generation based on gas & furnace oil • Gas becoming scarce • Exorbitant cost of imported oil/HSD • Double-edged sword of gas depletion and higher oil prices resulted in huge circular debt running in billions • The panacea lies in converting thermal power plants to cheaper fuels such as coal

  8. POSSIBLE SOLUTIONS TO IMPROVE PAKISTAN SECTOR • For conventional steam turbine thermal units, the possible option is to convert them to coal • The benefit of converting the furnace oil plants would be through savings on fuel cost component • Expedite import of gas or use alternative fuels available such as LNG for gas turbine or reciprocating engine

  9. CANDIDATE PLANTS FOR COAL CONVERSION

  10. ISSUES ON CONVERSION OF STEAM POWER PLANTS TO COAL • Involvement of new Capital Costs • Outage time to dismantle old boilers and assemble/commission new ones • Additional auxiliary consumption thereby reducing the net generation capacity • Higher O&M costs • Limitation of space for coal storage & ash handling • Probable reduction of efficiency • Availability of coal, and • Environment degradation

  11. IMPLEMENTATION MECHANISM FOR CONVERSION TO CHEAPER FUELS • Conversion of GENCOs plants to cheaper fuels is visualized through induction of private sector contractor(s) in Public Sector Power Stations (concept approved) • IPPs’ conversion is visualized through devising a Policy Regime (in process of approval)

  12. CONVERSION OF GENCOs TO CHEAPER FUEL THROUGH INDUCTION OF PRIVATE SECTOR GENERATIONKEY FEATURES Induction of O&M Contractor for 10 years through open bidding No retrenchment of existing staff; No capital expenditure and no payment of mobilization advance by GENCOs / Government of Pakistan (GOP) No upward revision of tariff due to induction of O&M Contractor; Evaluation & Selection of O&M Contractor through a criteria based on benefit sharing, percentage of which to be determined through bidding process;

  13. CONVERSION OF IPPS ON CHEAPER FUELSSALIENT FEATURES • IPPs to carry out due diligence/feasibility study individually for cheaper alternative fuels as per their technologies. • IPPs be given one year (or less if their conversion plan require less time) for conversion during which they will be provided half of their Escalable tariff component (which covers their returns etc) and full Non-Escalable tariff component (which covers their debt servicing). • Any saving that would be achieved due to switching of fuels be shared equally amongst the IPPs and the power purchaser.

  14. CONCLUSION Conversion of existing thermal power plants to coal will develop the market for new coal mines – hence eliminate the MARKET RISK especially for development of Thar Coal

  15. THANKS

  16. PROBABLE BENEFITS FROM CONVERSION OF SUITABLE CANDIDATE PROJECTS TO COAL

  17. BACKUP SLIDES

  18. CONVERSION ON CHEAPER FUELSSALIENT FEATURES • Power Purchaser be allowed to legalize the arrangement and any extensions in the Term of Power Purchase Agreements with IPPs pursuant to 1994 Policy through Side Agreements without requiring any approval from any government agency / regulator. For IPPs pursuant to 2002 Policy necessary permission of regular shall be needed. • Power Purchaser to have right to negotiate and schedule outage timings and number of units at a time for conversion, as well as fix priority of IPPs if more than one IPP approach to it for conversion, and the feasibility study favours one over the other. • Customs duty at the rate of 5% on the import of equipment, machinery and spares for carrying out Balancing, Modernization and Replacement (BMR).

  19. PRE-DEVELOPMENT OF COAL MARKET – A BASIC INGREDIENT FOR DEVELOPMENT OF SINDH COAL Conversion of existing thermal power plants will pre-develop the market for new coal mines – hence eliminating the MARKET RISK especially for development of Thar Coal. As such we expect fullest support of GOS in our venture.

  20. COST – BENEFIT ANALYSIS (GENCOS)

  21. COST – BENEFIT ANALYSIS (IPPS)

More Related