Physical Inventory Counting Plan on 30 th Dec

Physical Inventory Counting Plan on 30 th Dec. 7 th Dec 2013. 1. Org chart for inventory management. General Manager HS Yoon. Operation Manager Ken Lee. ㆍ Core Team : 2 ㆍ Counting Group : 14 ㆍ Checking&QAD Group : 2. Champion JW Park. Core team #1. Core team #2. Core team #3.

uta-larson
Download Presentation

Physical Inventory Counting Plan on 30 th Dec

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Physical Inventory Counting Plan on 30th Dec 7th Dec 2013

  2. 1. Org chart for inventory management General Manager HS Yoon Operation Manager Ken Lee ㆍCore Team : 2 ㆍCounting Group : 14 ㆍChecking&QAD Group : 2 Champion JW Park Core team #1 Core team #2 Core team #3 Core team #4 Core team #5 Core team #6 Quality Daniel Lee Production SY Ahn Matl’ & Logis Joonhi Ahn R & D Michael Chai QAD JH Joo Value Control Anthony Seo E A B F J H Checking Counting Tag & Controling QAD B D I L Test Room & Office G K

  3. 2. Counting Team & Members

  4. 3. Responsibilities Coreteam leader Member organize & training Guarantee counting accuracy Communication Managing counting team and area Coreteam member Communication with team leader Area arrangement Counting & writing on the tag

  5. 4. Location allotment –In-house G H L Tent I R-BSM line # 1130 W/House for R FG FG #2000 J Testroom FG #2000 FG #2000 Shipping & receiving C E F K Theta BSM line #2 # 1100 FG #2000 W/House Failure #7000 Matl’ #1000 Theta BSM line #1 # 1100 Tau #1110 A B D

  6. 4. Location allotment-Depot & Customers 1) Depot Kyeongbo (excluding CS Gears) Hyeondae-Naeja M N 2) Customers HMC Ulsan KMC Hwasung M O 3) Supplier temporary consignment Dongbo (Theta BSM shaft  700set, R-eng CM Shaft  565 pcs)

  7. 5. Physical inventory counting Tag

  8. 6. Master schedule

  9. Thank you…