1 / 8

RGVSG RENEWABLE ENERGY PROJECT FACT SHEET COMMUNITY OUTREACH PROGRAM

RGVSG RENEWABLE ENERGY PROJECT FACT SHEET COMMUNITY OUTREACH PROGRAM. RGVSG RENEWABLE ENERGY PROJECT FACT SHEET COMMUNITY OUTREACH PROGRAM.

uzuri
Download Presentation

RGVSG RENEWABLE ENERGY PROJECT FACT SHEET COMMUNITY OUTREACH PROGRAM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RGVSG RENEWABLE ENERGY PROJECTFACT SHEETCOMMUNITY OUTREACH PROGRAM

  2. RGVSG RENEWABLE ENERGY PROJECTFACT SHEETCOMMUNITY OUTREACH PROGRAM • The RGVSG propose to construct a $23.8 million Clean Energy and Air Project through the construction of a Bagasse (cane stalk) Handling System and the installation of a new High-Efficiency Boiler and Turbo-Generator. • The proposed Project may be financed up to 50% of the Project Costs by the North American Development Bank (NADB). The remaining project costs will Vbe financed through a combination of the CoBank loans and RGSG equity. NADB has hired Pollutech International for technical review of the Project. • Prior to approval by NADB for financing, the Border Environment Cooperation Commission (BECC) must certify the Project in accordance with the following criteria: BECC CRITERIACOMPLIANCE Alternative Analysis  International Treaties and Agreements  Human Health and Environment  Compliance with State and Federal Regulations  Environmental Impact Assessment  Technical Feasibility  Appropriate Technology  Operation and Maintenance Plan  Design Regulations and Standards  Financial Feasibility  Community Participation Plan 

  3. RGVSG RENEWABLE ENERGY PROJECTFACT SHEETCOMMUNITY OUTREACH PROGRAM • The RGVSG Cooperative has a membership of 127 sugar growers and is the only cane sugar mill in the State of Texas • The RGVSG members actively farm up to 47,000 acres of sugar cane (3% of the arable land in RGV) yet provides almost 12% of the GDP in the RGV ($75M/Yr) • The proposed project includes… - conversion of all bagasse conveyors to fully automated belt conveyors - expansion and upgrade of the bagasse storage building - conversion of the boiler building to handle the modified bagasse conveyor system - installation of a new high efficiency boiler - new condensate storage tank - rebuilt 6,000 KW turbine generator • Project Benefits include: - Reduction in use of fossil fuels through the implementation of a renewable energy source through production of 11 MW leaving 5 MW for sale - Eliminates the need for purchase of 1.7 MW of outside energy that will be available for use by others - A 42% reduction in total mass of air pollutants - Increased level of service to RGVSG members

  4. RGVSG RENEWABLE ENERGY PROJECTFACT SHEETCOMMUNITY OUTREACH PROGRAM • Project Costs and a Brief Financial Analysis are shown in the table below. • The RGVSG expect to receive the draft permit from the TCEQ for the Mill Operations – issuance of final permit within 60 days after public comment period (Consolidated Permit No. 114) • The RGVSG is defined as a “major stationary source” under the Federal Clean Air Act • The RGVSG also has a Cane Burning Permit

  5. RGVSG RENEWABLE ENERGY PROJECTFACT SHEETCOMMUNITY OUTREACH PROGRAM • RGVSG under their current Air Quality Permit is allowed the following: - 2,490.4 tpy CO - 0.54 tpy SO2 - 233.2 tpy Nox - 222.08 tpy CO - 443.88 tpy VOC • As a result of the above-listed permit loadings, the RGVSG Mill is subject to PSD Regulations (Prevention of Significant Deterioration) thus must conduct analysis of BACT and these findings are listed below: - Growth Analysis – No additional air emissions from off-site growth - Air Quality Impact Analysis – modeling analysis adequately evaluates the total ground level concentrations of NO2 from improvements - Soils/Vegetation Analysis – the projected NO2 concentrations are below the standards and significant level thus no adverse impact - Visibility Impairment Analysis – plant is located in sparsely populated area with no scenic vistas or airports thus no impairment - Area Impacts – the plant is located 1,110 km from the closest Class 1 Area (Big Bend) thus no impact (>100 km separation)

  6. RGVSG RENEWABLE ENERGY PROJECTFACT SHEETCOMMUNITY OUTREACH PROGRAM • PROJECTED EMISSIONS are compared to existing in the table below… 1 – Actual reported emissions based on stack testing of October 2001 2 – Projections from Pollutech Analysis – Boilers #1 to #4 at 34% and new Boiler at 90%

  7. RGVSG RENEWABLE ENERGY PROJECTFACT SHEETCOMMUNITY OUTREACH PROGRAM • TC&B has provided an environmental assessment of the project in support of the Step 2 Report • These findings are summarized below: - Air Quality impacts are significantly reduced - Project promotes the use of renewable energy sources - Project reduces reliance on fossil fuels - There are no water/wastewater issues, Plant is effectively Zero Discharge although a Discharge Permit is in effect • RGVSG has a Stormwater Pollution Prevention Plan with proactive monitoring • Cumulative Impacts are positive to the environment • Positive socioeconomic impact through short-term impacts due to construction and long-term due to increased sustainability and efficiency • RGVSG is proactive towards environment as evidenced by P2 Site Assistance Visit/Small Business Compliance Audit/TCEQ Pilot EMS Program

  8. RGVSG RENEWABLE ENERGY PROJECTFACT SHEETCOMMUNITY OUTREACH PROGRAM • Project approval by BECC scheduled for March 27, 2003 • Completion of PPA and Loan Closings in late 2003/early 2004 • Completion of Bagasse Handling Facilities in 2004 • Completion of Boiler/Generator Facilities by April 2005 (12 months lag time from order to delivery of boiler) • The RGVSG will hold two public meetings on January 23, 2003 and February 3, 2003 at the offices of the RGVSG at 6:00 PM. The public is welcome to attend and if you cannot attend one of the meetings, please submit written comments, letters of support or non-support to the following address: Rio Grande Valley Sugar Growers, Inc. P.O. Box 459 Santa Rosa, Texas 78593 Attention: Jack Nelson, President • Comments will be accepted up to February 3, 2003

More Related