200 likes | 218 Views
RF Gun Status LCLS Facility Advisory Committee Meeting October 26, 2005. Mechanical design review (08/05) Commissioning plan Cathode development Response to FAC recommendations. RF Gun Mechanical Design Review. Presentation of mechanical design with RF and thermal simulations.
E N D
RF Gun StatusLCLS Facility Advisory Committee MeetingOctober 26, 2005 Mechanical design review (08/05) Commissioning plan Cathode development Response to FAC recommendations
RF Gun Mechanical Design Review • Presentation of mechanical design with RF and thermal simulations. • Mechanical design commended by review committee. • Concerns • Heating at cathode/gun RF joint and coupler irises. • Damage from high flow in cooling channels. • Recommendations • Improve cooling design. • RF reflection in waveguide pumping slots acceptable. • Make two guns with tree sets of parts. • Start load lock development program. • Response • Water flow rate lowered. • Radii on ports increased to limit pulse heating. • Cathode plate thickened.
Gun and Solenoid Courtesy of E. Jongewaard
Water Flow Velocity Reduction Courtesy of E. Jongewaard
Gun Commissioning Schedule • Fabrication - 01/06 • Scheduled in SLAC Klystron department. • Cold test - 04/06 • Characterize gun. • Bead pull/drop measurement (use dummy cathode?). • Cathode plate tuning with 1st cathode. • Cathode preparation - 06/06 • Characterize 2nd cathode. • QE measurement, H+ ion cleaning. • Measure surface roughness & contaminants. • Gun & Solenoid integration - 06/06 • Assemble on common girder. • Magnetic measurement with dummy cathode. • Install cleaned 2nd cathode and retune. • Hot test - 08/06 • Details follow. • Installation & commissioning at S20 - 12/06 • See next presentation.
RF Gun Preparation • Part of injector commissioning schedule
Gun Hot Test • Objectives • Vacuum bake to 10-10 Torr. • Stable 120 MV/m operation. • Demonstrate 130 MV/m. • Demonstrate 120 Hz operation (3.5 kW thermal load). • Measure thermal distribution with low & high RF power. • Measure Cell field balance at high RF power. • Procedure • Install assembly in Klystron department and bake. • RF processing. • Full characterization. • Test temperature control?
Gun Hot Test Setup • Hardware from GTF • YAG/FC • Solenoid power supply • Thermal management • Cooling without temperature feedback • Track RF frequency with gun temperature • Controls • LLRF • Parameter logging • Algorithm for automatic processing Pump Gun Valve YAG/FC To Klystron Wave Guide Solenoid Pump
Measurements for Gun Conditioning • Gun temperatures (RTD’s) • W/G and FC vacuum pressure • Klystron drive power • Gun forward/reflected power • Half and full cell probes • Dark current in FC • Image of dark current (YAG) • RF breakdowns
Open Issues • Hot test schedule and location • PEP test bunker in Klystron Department • Available 08/06 • Sector 20 • Before, during, or after 2006 downtime (08/06-11/06) • More details in next presentation • Cooling water for gun • Stand alone 4 kW chiller? • Use facility water?
Cathode Development* • Presently no process to improve and control QE of LCLS cathodes. • No load lock in LCLS budget. • Need for improved cathode installation procedure. • Operational contamination requires in-situ cleaning. • Avoid risky gun baking and laser cleaning *Courtesy of D. Dowell
In-Situ Cleaning Methods • H-beam cleaning • Use ~1keV H-beam. • Cleans 1cm diameter area. • Requires no reconfiguration of gun system. • Benign to cathode surface. • H-plasma cleaning • Produce plasma inside gun volume. • Plasma excitation with RF • Only cleans region of high E-field. • Plasma excitation with DC • Only cleans region near electrodes.
H-ion Gun Gun Solenoid LCLS Min QE 2x10-5 at 255 nm Valve H-Beam Cleaning Results & Installation on Gun Experimental results from SLAC Physical Electronics Lab See D. Dowell et al., FEL2005 Conf.
Proposed Three Step Plan • Compare cathode surface processing with H+-beam vs. H+-plasma. • Find best procedure to clean, transfer, and install cathodes for LCLS gun 1. • Develop in-situ cleaner for LCLS gun 2. • Thermal emittance measurement not part of this plan.
Laboratory Test (Part 1) • Goals • Comparison of H-beam and H-plasma cleaning. • Find optimum materials and fabrication techniques. • Simulation of cathode transfer and installation effects. • Compare with theory. • Plan • Testing of small samples in SLAC PE lab. • Uses existing surface diagnostics equipment. • Construct H-plasma cleaner. • Result • Capability for H-beam and H-plasma cleaning & measured data.
Cathode Cleaning and GTF Test (Part 2) • Goals • Test robustness of cleaned cathodes for installation procedure and improve procedure for LCLS. • Quantify effect of gun bake on QE. • Plan • Characterization and H-beam cleaning of GTF cathodes in SLAC PE lab. • Transfer and test cathodes in GTF gun. • Compare lab QE measurement with operational QE. • Result • Improved procedure for installing well characterized, clean LCLS cathodes.
In Situ Cleaning for LCLS Gun 2 (Part 3) • Goals • Design and build cleaner system for LCLS Gun 2. • Find operating parameters for H+ source. • Plasma cleaning with RF, compare with bake. • Plan • Install and test system on existing chamber in PE lab. • Move system to LCLS Gun 2 and test. • Test with RF? • Result • Complete gun assembly with cleaner ready for installation at Sector 20.
Funding Status • BCR requested for part 1. • BCR in preparation for part 2. • Request for part 3 when results from parts 1 and 2 available.
Response to FAC Recommendations • Completion of second gun encouraged. • Fabrication of second gun scheduled with first gun. Will be available as complete system with solenoid as fast backup at sector 20. • Investigate gun wake field effects. • Large energy spread in GTF gun contributed to pi-0 mode beating. Should not occur in LCLS gun with 15 MHz mode separation. PIC simulations planned for next year. • Continue effort on H+ ion cleaning of cathode. • Budget modified to pursue cleaning and test on second gun. • Develop permanent facility for gun testing. • No decision made yet, but funding for GTF continued through FY2006.
Summary • Gun mechanical design completed. • Fabrication of gun scheduled. • Commissioning plan in progress. • Funding for cathode development underway.