WS Infrastructure Programme Q uarter ly Workshop KWAZULU-NATAL Presented by : M. Ngxongo

WS Infrastructure Programme Q uarter ly Workshop KWAZULU-NATAL Presented by : M. Ngxongo Regional Project Manager: WSRBIP Date: 31 October 2013. WS Infrastructure Programme : Quarterly Workshop. Contents. A: Expenditure Status 2013/14 RBIG MWIG ACIP NTP B : Key Challenges

virgil
Download Presentation

WS Infrastructure Programme Q uarter ly Workshop KWAZULU-NATAL Presented by : M. Ngxongo

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WS Infrastructure Programme Quarterly Workshop KWAZULU-NATAL Presented by: M. Ngxongo Regional Project Manager: WSRBIP Date: 31 October 2013

  2. WS Infrastructure Programme: Quarterly Workshop Contents A: Expenditure Status 2013/14 • RBIG • MWIG • ACIP • NTP • B: Key Challenges • C: Project to be “Fast Track” • D: Projects to be Launched • E: Way forward

  3. A1. RBIG : Expenditure 2013/14

  4. A1. RBIG : Expenditure 2013/14

  5. INVOICE STATUS AS AT 29 OCTOBER 2013

  6. A2. MWIG: Expenditure 2013/14

  7. A2. MWIG: Expenditure 2013/14

  8. A2. MWIG: Expenditure 2013/14

  9. A2. MWIG: Expenditure 2013/14

  10. A2. MWIG: Expenditure 2013/14

  11. A2. MWIG: Expenditure 2013/14

  12. A3. ACIP : Expenditure 2013/14

  13. A3. ACIP : Expenditure 2013/14

  14. A3. ACIP : Expenditure 2013/14

  15. A3. ACIP - Acceleration – Action Plans

  16. A3. ACIP - Acceleration – Action Plans

  17. A4: NTP – Expenditure 2013/14

  18. A4: Graphical Representation NTP, KZN

  19. A4: Progress per WSA

  20. B: Key Challenges RBIG • Irregular appointment of ISD Consultants. • Funding shortfall of projects • Final approval of the Greater Bulwer Scheme • Sluggish in flow of co-funding portion of funding • Additional cost of project value due to terminated contracts. • Non-Performing DM’s – UGU DM. they are under resourced resulting in poor management.

  21. B: Key Challenges RBIG • DMs delaying to pay contractors, and contractors constantly have to leave site e.g. uMzinyathi DM contractors MWIG • Delays have been experienced in getting environmental approvals (e.g. KwaSithole Project) • Delays have been experienced in appointing specialised contractors (e.g. Nondweni WTW) • Project has been hampered with rain (e.g. Nondweni WTW)

  22. B: Key Challenges on NTP NTP • Protracted SCM procedures within WSAs. Unreasonable amount of time to get contractor appointed • Having to initiate, implement and close out a project all within the space of a year • Weak WSAs i.e. inherent problems in their finance and PMU departments • Non compliance of WSAs – inability to submit invoices and supporting documentation timeously • Non payment of contractors by WSAs due to poor project management within the WSAs • Lack of skilled human resources within the WSAs

  23. C: Project to be “Fast Track” • ZULULAND DM: • Mandlakazi WTW to enable reliable supply to Hlabisa

  24. D: Projects to be Launched • Middledrift WTW – 26 November 2013 • Hlabisa BWS – 30 November 2013

  25. E: Way forward • National office to advice in time if additional funding will be made available for the ZDM projects that will be half complete should additional funding not be made available i.e. Mandlakazi WTW, as well as the completion of uSuthu BWS

  26. End