1 / 21

Modern Building: Green Library

Modern Building: Green Library. Eric Strafelda Tyler Mitchell Jordan Timmersman. NDSU Modern Building. 300,000 sqft (3x the size of the current library) Site location: East of Memorial Union 6 floors Two roof areas that allow for solar panel Allows for sunlight to be utilized fully.

vivien
Download Presentation

Modern Building: Green Library

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Modern Building: Green Library Eric Strafelda Tyler Mitchell Jordan Timmersman

  2. NDSU Modern Building • 300,000 sqft (3x the size of the current library) • Site location: East of Memorial Union • 6 floors • Two roof areas that allow for solar panel • Allows for sunlight to be utilized fully

  3. Requirements • Electrical Engineering Design – Blue Prints • Electrical Engineering Specifications • Electrical Engineering Studies • Solar Roof Study

  4. Meeting with Architect • We met with the architect and got the AutoCAD drawings form him. • He wanted the building to be as green as possible • Wanted us to design for the following: • Efficiency • Cost • Light Quality

  5. Meeting with NDSU Facilities • We talked with Brent Dekrey about seeing what the current library has in it. • Library is provided heat from steam plant • Has a 1200A service • Needed to have chillers and air handling units in our calculation for new library. • Roughly 100,000 sqft • Has a 100 kW backup generator

  6. Service Sizing Calculations • Receptacle Loading: All loading is unknown for our building so we assumed a 1 VA per square foot • 1VA*1VA*300,000sqft = 300,000VA • General Lighting: All lighting is unknown for our building so we assumed a 3.5 VA per square foot • 3.5 VA was found in code book Sec. 220.12 • 3.5VA*300,000sqft = 1,050,000VA

  7. Service Sizing Calculations • Lighting Demand Factor: Most of your lighting loads are considered to be a continuous load • 25%*General Lighting Load = 262,500 VA

  8. Service Sizing Calculations • Motor/Mechanical Loads • 1 CFM per sqft and 340 sqft per ton of coolant • With 300,000 sqft over 6 floors that is 50,00 sqft per floor. With 1000 ton chiller. • 1000 ton chiller = 3500 kW • (6) 50,000 Air Handling Units (AHU) • 2 motors rated at 75 hp motors • 6 150 hp motors for AHU’s

  9. Service Sizing Calculations • Combining Motor/Mechanical Loads • According to NEC section 440.7 you use 125% of your highest rated motor and then face value for all other loads. • 150 hp X 746 W/hpX125%=140,000 W • 5 X 150 hp X 746 W/hp=560,000 W • 3500 kW for the chiller • Total Motor Load of 700 kW

  10. Service Sizing Calculations • Combing all the numbers previously found. • Total VA=2,312,500 • VA=V*I*1.73 • V=480V • A=2,786.14 • Using NEC section 240.6 We selected a service size of 3000 Amps

  11. PV Economic Study • One of our major objectives in this project was to be able to work with an outside client such as an architect. • Our client asked us to provide an economic study to see if installing a photovoltaic array would be a wise investment.

  12. PV Payback Analysis

  13. PV Fringe Benefits • Some Fringe Benefits that are not related to direct energy cost analysis include: • Educational • Thermal • Demand Savings • Power Quality • Utility Buyback • Environmental • Public Perception

  14. PV Analysis Conclusion • Given the warranty/useful life a PV array is 20 years. The 13.32 payback period is very favorable • Including the 3.61 return on investment along with all fringe benefits. • We would recommend the inclusion of a PV array atop our modern building

  15. Project Status • We have successfully completed the deliverables for the first semester. • We had to do a little rearranging of our schedule and an updated timeline is on the following slide.

  16. Timeline

  17. Budget

  18. Summary • Using the NEC code book and information gathered from campus administrators we were able to select a service size of 3000A • Using engineering economic analysis we were able to accurately predict the cost of a PV Array installation and recommend its inclusion. • We are still on track to deliver our completed project next semester.

  19. Questions?

More Related