NO. Do not apply EVM. NO. Contract Value > $20M but <$50M. NO. Contract Value > $50M. Decision Process for EVM Application. Nature of Work Measurable. Cost or Incentive Contract?. Did MDA approve waiver for FFP?. NO. YES. NO. YES. YES. Did PM approve EVM
E N D
NO Do not apply EVM NO Contract Value >$20M but <$50M NO Contract Value>$50M Decision Process for EVM Application Nature of Work Measurable Cost or Incentive Contract? Did MDA approve waiver for FFP? NO YES NO YES YES Did PM approve EVM based on risk assessment? Contract Value <$20M YES NO • Contract = contracts, subcontracts, intra-government work agreements, other agreements • All $ thresholds are in TY • If contract type is mixed, then apply guidance separately to different parts of contract YES Apply EVM (Compliance with No Validation) YES Apply EVM (Compliance with Formal Validation) YES