1 / 32

La Crosse 161 kV Capacitor Addition

This document outlines the area system deficiencies and planned projects for the La Crosse and New Richmond areas in Wisconsin. It provides updates on progress since the last presentation and discusses next steps for addressing load serving problems and voltage issues.

weatherly
Download Presentation

La Crosse 161 kV Capacitor Addition

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. La Crosse 161 kV Capacitor Addition Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline

  2. Outline • Area System Deficiencies • Planned Project • Next Steps

  3. Area System Deficiencies • Summer 2008, at least 50 MVAR of capacitors are needed at La Crosse with Genoa 3 offline, French Island offline, and Alma – Marshland out • Must sustain 0.95 pu voltage at French Island 69 kV bus • French Island startup issues • In 2011, necessary capacitance increases to 110 MVAR

  4. Area System Deficiencies • Capacitance also needed at Monroe County Substation • Outage of La Crosse – Monroe County 161 kV line causes low voltage at Monroe County in 2011.

  5. Planned Project • Install two 60 MVAR capacitor banks at La Crosse Substation • Temporary solution until CapX line is in service • Will provide reliable source of power • Decrease reliance upon area 161 kV lines • Considering placing one of the banks at Monroe County Substation • 161 kV tie strong enough to supply enough support to French Island • Would support Monroe County in case of outage of La Crosse – Monroe County 161 kV line

  6. Wisconsin Study Update Eau Claire and New Richmond Northern MAPP Subregional Planning Group April 3, 2007 Daniel Kline

  7. Outline • New Richmond Area • Various Load Serving Problems • Update on Progress Since Last Presentation • Eau Claire Area • Various Load Serving Problems • Update on Progress Since Last Presentation • Next Steps • Questions

  8. New Richmond Area

  9. Description of Area • Located in Western Wisconsin • St. Croix County • Just across Minnesota border, near I-94 • Area fed by 161 kV sources and 69 kV subtransmission • Load belonging to NSPW and DPC • Lines belonging toNSPW and DPC

  10. Load Area 2008 2011 2016 New Richmond 45.4 MW 53.1 MW 63.7 MW DPC N-60 46.0 MW 52.0 MW 63.1 MW Total 91.4 MW 105.1 MW 126.8 MW Description of Area • Two distinct load-serving areas • New Richmond • Somerset, Osceola • Load Growth: • Total load growth of over 30 MVA in 8 year period from 2008 to 2016 • Bedroom communities for Twin Cities growth

  11. St. Croix Falls Apple River Sand Lake Lk. Camelia Bear Trap Griffin St. Osceola Farmington Clear Lake New Richmond Houlton Roberts Pine Lake Kinnickinnic Willow River Rush River Troy Crystal Cave Area System Deficiencies • New Richmond Voltage • Osceola Voltage • Autonomy of 69 kV lines from Pine Lake • Chisago – Apple River Construction

  12. Description of Area

  13. Description of Problems • Low voltage at New Richmond during outage of Pine Lake – New Richmond 69 kV line • Low voltage at Osceola during outage of Osceola – Osceola Tap 69 kV line • Overload of River Falls 115/69 kV transformer during outage of Osceola – Osceola Tap 69 kV line • Overload of Pine Lake 161/115 kV transformer during outage of King – Willow River 115 kV line • Normal Overload of Pine Lake – Rush River 69 kV line

  14. Description of Problems • High load growth throughout area • Installation of Chisago Line Project will require extended outage of Osceola – Osceola Tap 69 kV line • No room for expansion at New Richmond Substation • No room for expansion at Rush River Substation

  15. Project Plan • Multiple Independent Projects to work together • 10 MVAR Cap Bank at New Richmond – Under Construction • Three Lakes Substation – June 2009 • 5.4 MVAR Cap Bank at Osceola – June 2009 • Relocate Rush River Substation and cut over to 161 kV – June 2009 • Rebuild Osceola to Sand Lake 69 kV Line – June 2009 • Construct Somerset Sub – June 2010 • Construct Stanton Sub – December 31, 2010 • Construct Somerset to Stanton 69 kV Line – May 31, 2011 • Complete installation of Chisago Line Project – May 31, 2011 • Construct Poplar Lake Sub & 161/69 kV Transformer – May 31, 2011

  16. St. Croix Falls Apple River Sand Lake Lk. Camelia Bear Trap Griffin St. Osceola Farmington Clear Lake Somerset Substation Stanton Substation New Richmond Three Lakes Substation Houlton Roberts Pine Lake Kinnickinnic Willow River Rush River Troy Crystal Cave Planned Projects • Three Lakes Substation • Planned Somerset Substation • Stanton 69 kV Switching Station • Somerset to Stanton 69 kV Line

  17. Where Are We Now? • Projects have been through internal review process • Budget process for 2008-2012 is underway • Anticipate permitting and material procurement underway in 2008 • First stages of completion in 2009, finishing in 2010

  18. Next Steps • Coordination work for Wisconsin CPCN filing • External coordination for necessary interconnections • Working with DPC to determine ownership model for Poplar Lake Substation

  19. Eau Claire Area

  20. Description of Area • Located in West-Central Wisconsin • Eau Claire & Chippewa Counties • About an hour east of Twin Cities on I-94 • Area fed by 345 and 161 kV sources and 69 kV transmission • Load belonging to NSPW and DPC • Lines belonging toNSPW and DPC

  21. Load Area 2008 2010 2012 2014 2016 Chippewa Falls 84.9 MW 88.2 MW 91.5 MW 94.9 MW 98.2 MW Eau Claire 232.0 MW 240.6 MW 250.1 MW 259.5 MW 269.3 MW Total 316.9 MW 328.8 MW 341.6 MW 354.4 MW 367.5 MW Description of Area • Two distinct load-serving areas • Eau Claire • Chippewa Falls • Load Growth: • Total load growth of over 50 MVA in 8 year period from 2008 to 2016

  22. Description of Area Hydro Lane Wissota DPC Elk Mound Wheaton Jeffers Road Eau Claire Seven Mile

  23. Description of Area

  24. Description of Problems • Eau Claire transmission system is designed to rely upon Eau Claire 69 kV bus • Eau Claire 161/69 kV transformers are heavily loaded and cannot endure loss of parallel bank • Eau Claire substation is crowded and not enough space exists to increase the size of the existing 161/69 kV banks • Increasing size of banks would require moving to non-standard bank sizes

  25. Description of Problems • During peak load conditions, 69 kV system to north overloads • DPC system served out of Seven Mile overloads for various contingencies • High load growth throughout area • Interconnection requests at Hallie Substation requrie auto-transfer scheme to be turned off • Area transmission system highly susceptible to fluctuations in Chippewa River generation

  26. Final Recommendation • Re-terminate Wheaton to Presto Tap 161 kV line at Eau Claire Substation • Replace existing Eau Claire – Hydro Lane 69 kV double-circuit line with single-circuit 161 kV line • Construct 161/69 kV substation (50th Avenue Substation) where double-circuit 69 kV line intersects Hydro Lane – Red Cedar 161 kV line • Construct single circuit 161 kV line from Eau Claire to 50th Avenue Substation • Convert Hallie Substation to 161 kV operation • Construct second circuit from Wheaton Tap to Wheaton to avoid parallel three-terminal lines

  27. Hydro Lane Wissota DPC Elk Mound Wheaton Jeffers Road Eau Claire Seven Mile Near-Term Plans • Eau Claire – Hydro Lane Conversion • DPC East Hallie

  28. Where Are We Now? • Projects have been through internal review process • Budget process for 2008-2012 is underway • Anticipate permitting and material procurement underway in 2008 • First stages of completion in 2009, final project completion in 2011

  29. Next Steps • Coordination work for Wisconsin CPCN filing • Working with DPC on long-term plan for Eau Claire Area – to begin summer 2007 • Potential for one or two new 161/69 kV substations in Eau Claire area to provide additional voltage support and off-loading of Eau Claire Substation 69 kV bus

  30. Initial Ideas • Options investigated with and without Chisago project • Necessity of Poplar Lake Substation and 161/69 kV transformer investigated

  31. Questions?