1 / 12

PU-PPPL Earned Value Management System Overview

Princeton University Plasma Physics Laboratory EVMS Certification Review. PU-PPPL Earned Value Management System Overview. Thomas Egebo October 4-6, 2011. Outline:. Background PU-PPPL EVMS Stewardship/Organization EVMS Description Summary. Background:. Purpose:

whitakerd
Download Presentation

PU-PPPL Earned Value Management System Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Princeton UniversityPlasma Physics LaboratoryEVMS Certification Review PU-PPPL Earned Value Management System Overview Thomas Egebo October 4-6, 2011

  2. Outline: • Background • PU-PPPL EVMS Stewardship/Organization • EVMS Description • Summary EVMS Certification October 4-6, 2011

  3. Background: Purpose: EVMS measures actual performance of work scope and the associated cost and schedule versus an agreed to baseline plan, while using disciplined means of baseline change control for documenting any changes to the agreed to baseline plan. Although we’ve been using EV at PPPL for quite awhile; since NSTX-U TPC > $50M the PU-PPPL contract with DOE requires compliance with DOE 413.3B which dictates EVMS Certification by DOE for Projects > $50M EVMS Certification October 4-6, 2011

  4. PPPL EVMS Stewardship: The Deputy Director for Operations has the ultimate responsibility for overall oversight and implementation of project management. Direct responsibility for the development and management of the PPPL Project Management System is delegated by the Deputy Director of Operations to the Project Management Officer who is supervised by the Associate Laboratory Director for Engineering and Infrastructure. The PPPL Planning and Control Division is the steward of the earned value management system policy and has authority delegated to ensure that projects follow established Laboratory policy, and by extension, applicable industry standard. EVMS Certification October 4-6, 2011

  5. PPPL Organization: EVMS Certification October 4-6, 2011

  6. EVMS Certification October 4-6, 2011

  7. PU-PPPL EVMS Complies with ANSI/EIA 748-B Standard for EVMS & is suited to the needs of PU-PPPL • Provides thorough planning of all work scope into finite elements • Integration of scope, schedule and cost objectives • Timely baseline establishment and control • Objective measurement of accomplishment against plan • Disciplined, summarized reporting • Analysis of significant variances, forecasted impacts and management actions to mitigate risk EVMS Certification October 4-6, 2011

  8. PU-PPPL EVMS Documents Project Management System Description (PMSD) addresses EVMS and contains the following supporting procedures: • Procedure 1 Project Execution Plan • Procedure 2 Work Breakdown Structure (WBS) • Procedure 3 Project OBS and RAM • Procedure 4 Control Accounts, Work Packages & Planning Packages • Procedure 5 Control Account Plan/Work Authorization • Procedure 6 Project Schedule • Procedure 7 Cost Estimating • Procedure 8 Monthly Status Reporting • Procedure 9 Change Control • Procedure 10 EVMS Surveillance & Maintenance EVMS Certification October 4-6, 2011

  9. PU-PPPL EVMS deployed at the Project Level Goal is deployment of a cost-effective system that provides PU-PPPL management with an effective tool for decision-making Each project determines their own • variance thresholds • control account levels • work authorization • change control thresholds • software tools/scheduling styles • risk management methodology • reporting suite and style Surveillance program will validate their implementation decisions EVMS Certification October 4-6, 2011

  10. PU-PPPL Projects Required to use Certified System Current: NSTX-Upgrade; CD-2 Dec 2010 {TPC=$94.3M} CD-3 Jan 2012 Future: PPPL Science & Technology Support Infrastructure Project; CD-0 Aug 2010 {TEC $53M-$59M} CD-1 2012 CD-2 2014 5 Other PU-PPPL Projects using EVMS as a tool(following the overall principles of 413.3B and EVMS but to a lesser degree of rigor) $0.3M to $2.6M EVMS Certification October 4-6, 2011

  11. PU-PPPL Projects Undergo Continuous Surveillance • NSTX-U Regular updates to internal Directorate (weekly and monthly) • NSTX-U Weekly Technical Meetings • NSTX-U Monthly Status Meetings • PPPL Project Status Review Board Meetings (PSRB) • NSTX-U Integrated Project Team Meetings (monthly) • NSTX-U Project Critical Decision Reviews • FES Program Office Reviews (quarterly) • Biannual Advisory Committee Reviews (e.g., PU PPPL Advisory Committee) • Annual internal EVMS surveillance reviews • Ad-Hoc Weekly/Daily meetings with PSO NSTX-U FPD EVMS Certification October 4-6, 2011

  12. Summary – PU-PPPL EVMS • Compliant with ANSI/EIA-748-B Standard for EVMS (i.e., meets the requirements of the 32 EVMS Guidelines embodied in the ANSI/EIA748; Standard for Earned Value Management Systems.) • Provides PPPL projects with timely and meaningful information to support program and project management as a decision enhancing tool and a critical component of risk management. PPPL’s EVMS: • Effectively integrates a project’s work scope, cost, and schedule into a single performance measurement baseline (PMB). • Reliably tracks planned value (PV) ,earned value (EV) actual cost (AC) of work performed • Provides performance measures against the PMB. • Provides means of identifying, reviewing, approving, and incorporating changes to the PMB. • Provides trend analysis and evaluation of estimated cost at completion. • Provides a sound basis for problem identification, corrective actions, and management re-planning. EVMS Certification October 4-6, 2011

More Related