An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. South Gas Regional InitiativeOpen Season France-SpainValidation of the results Madrid, 27 October 2009

  2. Test to validate capacity allocation • As required at the 8th SG meeting of of 27th April in Paris, a test to validate capacity allocation in France has been published in the information memorandum for the open season 2013 • This test has been presented at the 9th Stakeholders meeting of 15th July in Madrid and some clarifications were brought • No further comments were raised regarding this test • The test is related to investment validation on the French side of the interconnection between Spain and France

  3. Principles and priority of the test • General principle: • If less than 50% of the marketed capacity is allocated, then the capacity allocation will be considered as non valid and no capacity booking contracts will be signed • If more than 90% of the marketed capacity is allocated, then the capacity allocation will be considered as valid and the relevant contracts will be signed • If the capacity allocated lies between 50 and 90%, then the continuation on whether to continue the open season will be discussed • Priority given to Larrau: • Validation of Larrau • Then allocation up to the maximum capacity of Larrau • Remaining quantity taken into consideration to validate or not Biriatou • Validation of Biriatou

  4. Figures of the test

  5. Result of the test • The demanded quantity amounts to 249 GWh/j

  6. Application of the test • According to the test: • Larrau is validated but not Biriatou • CRE proposes to validate the results of the open season accordingly, i.e. to allocate capacity at Larrau but not at Biriatou

  7. Possible next steps • CRE considers that the strong demand in the direction France to Spain has to be taken into account: • It could be envisaged to re-offer the capacity at Irun/Biriatou during the binding phase of the open season 2015, together with the capacity of MidCat • In this perspective, TSOs could realise some complementary studies, in order to adjust, if necessary, the physical investments needed, the investment costs and the date of availibility of capacity