50 likes | 73 Views
South Eastern University of Sri Lanka. Progress Report on Construction Projects / Development Projects as at 31 st July 2015. Building Complex for Main Library. Total Cost Estimate : 200 Million Physical Progress : 100% Financial Progress : 100.62%.
E N D
South Eastern University of Sri Lanka Progress Report on Construction Projects / Development Projects as at 31st July 2015
Building Complex for Main Library • Total Cost Estimate : 200 Million • Physical Progress : 100% • Financial Progress : 100.62%
Building Complex for the Faculty of Management & Commerce • Total Cost Estimate : 160 Million • Physical Progress : 100% • Financial Progress : 95.74%
Building Complex for Faculty of Applied Sciences at Sammanthurai • Total Cost Estimate : 170 Million • Physical Progress : 100% • Financial Progress : 80.08%
Building Complex for Student Hostel & Staff Quarters at Sammanthurai • Total Cost Estimate : 149 Million • Physical Progress : 85% • Financial Progress : 47.02%