180 likes | 193 Views
FORM NOMENCLATURE AND SAFETY. What have we accomplished?. STRENGTH OF MATERIALS. TIMBER DESIGN. SOIL MECHANICS. STEEL DESIGN. Where do we go from here?. Book Overview. Chapter One- Introduction to Forming Chapter Two- General Objectives in Formwork Building
E N D
FORM NOMENCLATURE AND SAFETY What have we accomplished? STRENGTH OF MATERIALS TIMBER DESIGN SOIL MECHANICS STEEL DESIGN Where do we go from here? Book Overview Chapter One- Introduction to Forming Chapter Two- General Objectives in Formwork Building Chapter Three-Overall Planning for Formwork Chapter Four-Materials, Accessories, Proprietary Products Chapter Five -Load and Pressures Chapter Six- Form Design
Introduction to Forming What is forming and formwork? • Formwork is the total system of support • for placed concrete. • It is a major cost of a concrete structure • (it accounts for as much as 60% of the cost) What is its purpose? • to safely support the reinforced concrete in • its plastic state until it has reached adequate • strength What are the objectives of any form design? • the form design must provide the best quality, • safety and at also be economical
Introduction to Forming • the best quality entails: • 1. alignment to adjacent surfaces • 2. resistance to excessive deflections • 3. a good surface finish • 4. structural integrity to withstand service • loads • 5. its ability to use standard materials • 6. dimensional consistency or its repetitive • members Note: Safety and Economics will be covered in more detail later on
Introduction to Forming What kind of nomenclature or terminology is associated with forming? Form ties- installed through the forms to resist the bursting pressure exerted by the concrete. ( has a clamping device at each end for attachment to and support of the wales
Introduction to Forming Beam- horizontal structural load bearing member Braces- fastened to one side of the forms to prevent shifting when concrete is placed Formwork- the total system of support for freshly placed or partially cured concrete. This includes the mold or sheathing that contacts the concrete as well as supporting members
Introduction to Forming What kind of nomenclature or terminology is associated with forming? joists- horizontal members which directly support sheathing reshoring- the construction operation in which the original shoring is adjusted or replaced to support partially cured concrete and other imposed loads Sheathing - the material forming the contact face of forms and providing the resistance to the pressure of the freshly placed concrete Shoring(falsework)-the elements used , excluding the formwork, to support fresh concrete and/or structural members during construction(i.e. vertical posts, lateral bracing, etc.)
Introduction to Forming What kind of nomenclature or terminology is associated with forming? Sill(Mud Sill)-a member, usually wood, designed to distribute the vertical shoring loads to the ground or the slab below. Stringer(Ledgers)- horizontal structural members which directly support joists
Introduction to Forming Studs- members to which the vertical sheathing is attached and provide support for it, it is installed vertically Wales(Walers)-installed perpendicular to the studs in order to support the studs, to hold the studs in position, to ensure good alignment for the forms and to recieve the form ties
Introduction to Forming What kind of nomenclature or terminology is associated with forming? Cleat-small board used to connect formwork members or used as a brace Base Plate- a device used between post, leg or screw and foundation to distribute the vertical load(mudsill)
Introduction to Forming Strongbacks- installed perpendicular to wales to provide additional strength and rigidity to high forms Batten(Batten Strip)-a narrow strip of wood placed over the vertical joint of sheathing or paneling, or used to hold several boards together
Introduction to Forming What kind of nomenclature or terminology is associated with forming? Sources: Glossary refer to Appendix page A-3 Pictures with spec A-16 to A-20 Pictures of Vertical shoring 4-51 Pictures of Ties 12-19
Introduction to Forming What are the safety issues involving form design? Causes for Formwork Failures: 1.Improper or inadequate shoring 2. Inadequate bracing of members 3. Lack of control of rate of conc. placement 4.Improper vibration or consolidation of conc. 5.Improper or inadequate connections 6. Improper or inadequate bearing details 7.Premature stripping of formwork 8.Errors in placement of reshoring 9.Improper, or lack of, design of formwork 10. Inadequate strength of form material 11. Failure to follow codes and standards 12. Modifications of vendor-supplied equip. 13. Negligence of workers or supervisors
Introduction to Forming What are the safety issues involving form design? • Examples Formwork Failures: • 1.Improper or inadequate shoring • i.e wrong size(too small to carry the load • or too long and buckles) • 2. Inadequate bracing of members • lack of cross or horizontal bracing • the cross bracing is preferred • 3. Lack of control of rate of conc. placement • This causes excessive pressures • high discharge point causes impact loads • in cold conditions the setting rate is retarded • 4.Improper vibration or consolidation of conc. • internal problems- impact loads on members • external problems-liquefaction occurs, and • vertical sleaves vibrate out of plumb alignment
Introduction to Forming What are the safety issues involving form design? • Examples Formwork Failures: • 5.Improper or inadequate connections • Fasteners suitability (threaded vs. nails) • or inadequate number of nails • 6. Improper or inadequate bearing details • Shores placed directly on ground w/o plate • uncompacted or suitable soil conditions • insufficient thickness to bridge gaps • 7.Premature stripping of formwork • inadequate time duration to set or cure • 8.Errors in placement of reshoring • improper locations (introduce secondary • stresses) • insufficient quantity provided
Introduction to Forming What are the safety issues involving form design? • Examples Formwork Failures: • 9.Improper, or lack of, design of formwork • lack of basic design principles • use of too high allow stress values • insufficient loading consideration(i.e impact) • improper loading value(i.e. conc thickness) • 10. Inadequate strength of form material • i.e Construction grade vs. structural grade • damage due to use • insufficient & improper ties to multiple • members • 11. Failure to follow codes and standards • Failure to follow the ACI-concrete • NDS-wood • AISC-steel
Introduction to Forming What are the safety issues involving form design? • Examples Formwork Failures: • 12. Modifications of vendor-supplied equip. • proprietary equipment- misuse • 13. Negligence of workers or supervisors • untrained workers • poor supervision
Introduction to Forming • Inspection Stages recommended by ACI: • 1. Preliminary Inspection is after the forms • are built and prior to the oiling or re-bar • placement • 2. Semi-Final Inspection is prior to final • cleanup • 3. Final Inspection is immediately before • concreting to make sure surface is clean and • oiled • Recommendation: • During the concrete pouring listen to forms • for cracking and popping noise • look at all portions and check for • displacement of elements and vertical • misalignment
Introduction to Forming What are the safety issues involving form design? See Case Studies in 2-4 to 2-8