440 likes | 454 Views
Mississippi Riverbank Project (Final Presentation) May 14, 1999. Architect: . . . . . . . . . . . . Steve GEORGALIS . . . . . . Georgia Institute of Technology Structural Engineer: . . . Tomo CEROVŠEK . . . . . . University of Ljubljana
E N D
Mississippi Riverbank Project(Final Presentation)May 14, 1999 Architect: . . . . . . . . . . . . Steve GEORGALIS . . . . . . Georgia Institute of Technology Structural Engineer: . . . Tomo CEROVŠEK . . . . . . University of Ljubljana Construction Manager: . Jacky HO . . . . . . . . . . . . . . Stanford University Owner: . . . . . . . . . . . . . Ali AL-ALI . . . . . . . . . . . . .
Agenda • Project Introduction • Four Preliminary Design Alternatives • Final Design - A / E / C Solutions and Interactions • Learning Experience
Introduction • Building for Riverbank University in Sacramento • Virtual Project (Year 2010) • Produce 4 Alternatives and 1 Final Design • Practice A/E/C Interaction
Requirements • Architectural Requirements • Maintain Footprint & Transportation / Circulation • Occupancy, Security, Environmental (3 stories, total height 35’) • Structural Requirements • Load: Earthquake and Total Height of 35’ • Construction Requirements • Budget : $5,500,000 (Structural $550,000) • Time Budget : 12 months (ready in May 2012)
4 Alternatives 1 2 3 4 $4,500,000 $4,900,000 $4,700,000 $4,100,000
Alternative 3 3rd floor
Reasons for choosing Alternative 2 • Owner’s Decision Aesthetic and Challenging Design • Team’s Preference Attracting Glass Atrium Challenging Structural Systems Feasible in Time and Cost
Further Iterations and Evaluations A Meeting with Owner • Height Limit • Faculty Lounge • Atrium Design • Structural Materials Revised design Feedback on cost Revised design material choice Suggestions and changes E C Revised design Feedback on cost and constructibility
Discussion on Structural Materials • Prefab Steel Frame for Atrium • Cast-in-place Concrete Columns
Engineering: Loads • Live Loads: • Classrooms: 40 psf • Offices: 50 psf • Halls: 100 psf • Dead Loads: • Self weight, floor and partitions 30 psf • MEP 10 psf • Seismic Load: zone 3 (solid rock)
Typical members and connection • Beam spacing: 19’ • Typical column: 18’’x18’’ • Reinforcement: 3.5% • Typical beam: 16’’x20’’ • Foundations: 4’x4’
Construction: Schedule • Total Duration: 10 months • Milestone 1: Start of Concrete Superstructure • Milestone 2: Finish of Concrete Superstructure • Milestone 3: Finish of Glass Atrium
Construction: Milestone 1 • June 20, 2011 • Completion of • Foundation and • Auditorium • Start Concrete • Frames
Construction: Milestone 2 • Sept 20, 2011 • Completion of • Concrete Frame • Start Atrium
Construction: Milestone 3 • Dec 10, 2011 • Completion of • Atrium • Continue Interior • Construction
Construction: Equipment Excavation • 90,000 CF of soil Excavator Dump truck Cast-in-place Concrete • 3,500 LF of Columns • and Beams Pumper Truck Concrete Mixer Atrium Steel Frame • Max height: 36 feet Crane Truck
PUT A FINAL MODEL HERE FOR WRAP UP
A C E A C E Learning from AEC • Roles of A / E / C • New communication technology • New team working environment • Using 3D Model