An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab • New kappa not yet in operation

  2. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab

  3. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab I911-1 Diffraction station Under reconstruction

  4. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab I911-1 Diffraction station Under reconstruction I911-2 MX station Single-axis goniostat

  5. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab I911-1 Diffraction station Under reconstruction I911-2 MX station Single-axis goniostat I911-4 SAXS station Under commissioning

  6. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab I911-1 Diffraction station Under reconstruction I911-2 MX station Single-axis goniostat I911-5 MX station Single-axis goniostat New monochromator I911-4 SAXS station Under commissioning

  7. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab I911-1 Diffraction station Under reconstruction I911-2 MX station Single-axis goniostat I911-3 Tunable MX station Mini-kappa MK3 I911-5 MX station Single-axis goniostat New monochromator I911-4 SAXS station Under commissioning

  8. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab I911-3: Experiment station completely rebuilt March-May 2010 (new hutch, new experiment tables, new goniostat,...) Users during June 2010 Sample changer installation October 2010

  9. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab

  10. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab

  11. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab

  12. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab I911-3: Control software: spec and mxCuBE mini-kappa MK3: not yet used

  13. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab MAX IV New facility replacing the present MAX I, MAX II & MAX III storage rings (and the present FEL test facility) Consisting of: - 1.5 GeV ring (96 m circumference, 6 nm rad) - 3 GeV ring (530 m circumference, 0.3 nm rad, 19 straight sections available) - a short pulse facility that could be extended with a FEL

  14. Kappa meeting, EMBL, Grenoble, 20th September 2010 Status Report MAX-lab MAX IV Funding available for buildings and accelerator ... but not for the beamlines We hope to have funding for 7 beamlines this autumn including a microfocus MX beamline and possibly ahigh-throughput MX beamline.