INTERLINKING OF GODAVARI & YELERU RIVERS THROUGH PIPLMC PURUSHOTHAPATNAM LIFT IRRIGATION SCHEME AS ON 21.05.2017. PROJECT SCHEMATIC DIAGRAM. Pressure Main Length of 10.10 Km, 5 rows of 3.2 m dia MS pipes. River Godavari. Delivery Cistern @ Km 1.600. PIPLMC CANAL. Yeleru Reservoir.
E N D
INTERLINKING OF GODAVARI & YELERU RIVERS THROUGH PIPLMC PURUSHOTHAPATNAM LIFT IRRIGATION SCHEME AS ON 21.05.2017
PROJECTSCHEMATICDIAGRAM Pressure Main Length of 10.10 Km, 5 rows of 3.2 m dia MS pipes River Godavari Delivery Cistern @ Km 1.600 PIPLMC CANAL Yeleru Reservoir Pattisima LIS Purushothapatnam LIS Yeleru Reservoir Stage 1 Pump House (10 Pumps each 350 cusecs) YLMC Stage 2 Pump House (8 Pumps each 175 cusecs) PIPLMC CANAL @ Km 50.00 Pressure Main Length of 13.12 Kms, 2 rows of 3.2 m dia MS pipes Cross Regulator @KM 57.885 YELERU RIVER
Land Acquisition Stage-I: LP Schedules are submitted , Preliminary notification and Declaration are also completed. Payment was made for 143 no. of ryots to an amount of Rs.24.450 Crores and bills for 23 no of ryots are submitted to PAO for an amount of Rs.3.580 Crores for payment. Purushothapatnam Village : 96.82 Acs Vangalapudi Village : 4.88 Acs Chinakondepudi Village : 71.24 Acs Nagampalli Village : 33.41 Acs. Total : 206.35 + 47.80 (Govt land)= 254.15 Ac. Out of 334 Nos of ryots, 240 Nos of ryots are given consent to the revenue department to execute the work , out of 254.15 acres 183.89 acres (including govt land 47.80 Ac) are handed over to agency to execute the work. Stage II - LP Schedules are submitted and Preliminary Notification is completed. Ramavaram(V) : 12.67 Acs Marripaka : 18.44 Acs Gollagunta : 10.24 Acs Irripaka : 17.38 Acs Mamidada : 21.20 Acs Eleswaram : 17.17 Acs Kattumilli : 6.13 Acs Total : 103.23 Acs. Out of 7 Nos, 6 Nos (Ramavaram(V) .Gollagunta, Irripaka ,Maripaka, Eleswaram & Mamidada) Villagers are given consent to the revenue department to execute the work.
Alignment of Stage- II LENGTH OF PRESSURE MAIN = 13.12KM