An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Provisur / Mokena Equipment Manufacturing Process MPS Planning – Starts Planning Build Kickoff Move Date in/out based on EOD Planning Bills in System / Common LLT Parts Ordered EOD Kickoff Part Pick 1,200 Parts Eng Bills Selects Ordered Mokena Machine Build Build 6 weeks 600 Hours LLT Parts 24 weeks

  2. Provisur / Mokena Equipment Manufacturing Process SUPPLIER PARTS LATE SUPPLIER PARTS RGR’ED MPS WRONG / LATE PLANNING BILLS NOT RELEASED MPS Planning – Starts Planning Build Kickoff NO TIME TO REACT Planning Bills in System / Common LLT Parts Ordered Part Pick 1,200 Parts EOD Kickoff PARTS TAKEN FOR FIELD PARTS LOST/DAMAGED Eng Bills Selects Ordered DEF PARTS REACH FLOOR PICKING ISSUES CUSTOMER INFO LATE/REVISIONS PARTS ORDERED LTLT SUPPLIER CANT REACT MANPOWER ISSUES PART REVISION ISSUES ENG BILLS LATE/INCORRECT Machine Build NPD / PROJECT EMERGENCIES Build 5 weeks 600 Hours LLT Parts 24 weeks

  3. Provisur / Mokena Equipment Manufacturing Process MPS Planning – Starts Planning Build Kickoff Planning Bills in System / Common LLT Parts Ordered Part Pick 1,200 Parts EOD Kickoff Eng Bills Selects Ordered CUSTOMER INFO LATE/REVISIONS Eng/Sourcing working together to plan in advance as changes happen ENG BILLS LATE/INCORRECT Machine Build NPD / PROJECT EMERGENCIES Build 5 weeks 600 Hours LLT Parts 24 weeks

  4. Provisur / Mokena Equipment Manufacturing Process SUPPLIER PARTS LATE SUPPLIER PARTS RGR’ED MPS WRONG / LATE PLANNING BILLS NOT RELEASED MPS Planning – Starts Planning Build Kickoff Planning Bills in System / Common LLT Parts Ordered Part Pick 1,200 Parts EOD Kickoff PARTS TAKEN FOR FIELD PARTS LOST/DAMAGED Eng Bills Selects Ordered DEF PARTS REACH FLOOR PICKING ISSUES MANPOWER ISSUES TEAM NEEDS TO REVIEW GOING TO A PRE-BUILD PULL SYSTEM TO MINIMIZE THESE ISSUES PART REVISION ISSUES Machine Build Build 5 weeks 600 Hours LLT Parts 24 weeks

  5. Provisur / Mokena Equipment Ideal Process MPS Planning/ Contract P.O. for Supplier Capacity Planning WILL IMPROVE: SUPPLIER LATE SUPPLIER RGR’s MPS WRONG / LATE BILLS NOT RELEASED PARTS ORDERED LTLT PART LOST/DAMAGED MANPOWER ISSUES + REDUCED INVENTORY Pull system set up by supplier based on MPS & LT Supplier Assembly/ Kit Release Slack Time Mokena Prebuild/Kit Common/Select Builds Releases Slack Time EOD Kickoff Misc Parts / Selects Ordered Part Pick 300 Parts Specific Customs Ordered Eng Bills Machine Build Supplier Sub 100 Hours Sub Build 300 Hours Build 3 weeks 200 Hours

  6. BOM Review / MFG Strategy High / Low Inventory Value Example: Frames / Doors / Feet High / Low Labor Hours High / Low Quality/Fit Issues Best Mfg Strategy: Pre-assembled from Supplier High / Low Supplier Count Early / Late Assembly Sequence Technology High / Low High/ Low Inventory Value Example: Electrical Cabinet High / Low Labor Hours High / Low Quality/Fit Issues Best Mfg Strategy Pre-assembled at Mokena Pull System High / Low Supplier Count Early / Late Assembly Sequence Technology High / Low

  7. BOM Review / MFG Strategy High / Low Inventory Value Example: Frames / Doors / Feet High / Low Labor Hours High / Low Quality/Fit Issues Best Mfg Strategy: Pre-assembled from Supplier High / Low Supplier Count Early / Late Assembly Sequence Technology High / Low High/ Low Inventory Value Example: Electrical Cabinet High / Low Labor Hours High / Low Quality/Fit Issues Best Mfg Strategy Pre-assembled at Mokena Pull System High / Low Supplier Count Early / Late Assembly Sequence Technology High / Low

  8. BOM REVIEW

  9. Supplier Lead Time Reduction Working on actions on several fronts: • Best Fit / Find suppliers that can reduce manufacturing steps • Robinson / Ace – adding internal machining capacity • AMFEC / internal machining & anodizing • Increase capacity through adding suppliers • Large parts - adding Robinson / Trace-a-matic • Small parts – To add three in 2013 • Modify parts manufacture methods • Friction welding / low volume plated parts to SS • Reduce “Re-prioritization” from emergencies • Engineering / Rush parts outside of production requirements • Meeting with Eng. weekly to prepare supply base for NPD/Emergencies • Contract P.O.’s – for plated parts & machine parts • Negotiate releases and pre-build • Simplifying Repairs • Working with Harbor Mfg for quick on site service • Eliminate poor performing suppliers • Custom Rubber