1 / 16

Post Review of Procurement by World Bank

Post Review of Procurement by World Bank. Key Observations. States covered:. Assam Karnataka Maharashtra Uttar Pradesh. Key Observations. Key observations shared with the concerned States on 28 th July 2011 for comments. Post reviewed 130 contracts, at SPO and DPO.

yael
Download Presentation

Post Review of Procurement by World Bank

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Post Review of Procurement by World Bank

  2. Key Observations States covered: Assam Karnataka Maharashtra Uttar Pradesh

  3. Key Observations • Key observations shared with the concerned States on 28th July 2011 for comments.Post reviewed 130 contracts, at SPO and DPO. Summary of Observations ASSAM • Contract amount for procurement of school bag was ` 106.30 lakh but the payment made for ` 454.90 lakh without issue of repeat order or revision of purchase order. In excess of open tender threshold of US $ 300,000 equivalent

  4. Key Observations • Not maintained bidding period of 30 days for open tender of procurement of sitting mat • Exceeded the threshold of US$ 30000 for single contract for the purchase of 10 KVA generator under DGS&D Rate contract. • Computers and its accessories amounting to ` 349.55 lakh procured under DGS&D Rate contract instead of open tender. • Procurement of digital camera under limited tender was made inviting 4 quotations but 2 bidders were having the same address.

  5. Key Observations • Entire procurement cycle for the purchase of laptop was completed within two days. • Two bidding documents issued on the same day for purchase of water bottle for Class I & IV (` 184.78 lakh) and Class III & IV (` 171.28 lakh) which exceeded the open tender threshold of US $ 300,000 equivalent. • Delivery details and invoice details not made available during review for printing and supply of evaluation of workbooks for Class V. • Procurement process was not reviewed as per TOR for hiring of external auditors and internal auditors.

  6. Key Observations • Fraud and corrupt (F&C) indicator as the awadee is one among the related quotations submitted and effectively reduces the number of quotations for purchase of wooden cots. • Not stipulated rationale delivery period for purchase of stationery. • Payment was made based on provisional bill and delivery period not stipulated for purchase of generator period. • Delay in supply of stationery items. • Entire procurement cycle was compelted within 3 days and unrealistic delivery period for supply of furniture ,TLM and generator.

  7. Key Observations • All 3 quotations were in similar format and same hand writing. • The dates issued for work order and delivery / invoice / payment dates on the same day. • KARNATAKA • Restrictive tender clause and subjective evaluation. • Delay in delivery / supply of material. • Not indicated date of opening of quotation in RFQ • Purchase order does not indicate terms and conditions

  8. Key Observations • Single tender method adopted instead of limited tender. • Possible F&C for purchase of UPS . • Delay in issue of work order defeats the purpose of limited tender. • Invoice and delivery date before work order date. • Bid security DD having sequential numbers. • L1 and L2 share same telephone numbers. • In another case, L1 and L3 share same telephone numbers. • Date of delivery not available in file.

  9. Key Observations • Date of delivery, invoice details, payment details not available in file. • Brand specific procurement for Samsung Air Conditioner and V-Guard stabilizer. • Details not mentioned in RFQ and PO. • Deliverables on statutory auditors and internal auditors not complied. • Quantity of mathematics textbooks increased by 30%. • RFP and TOR are included qualification and evaluation criteria for appointment of District Engineers and Block Engineers.

  10. Key Observations • MAHARASHTRA • Splitting of requirements of computers to avoid open tender. • Purchase order under DGS&D Rate Contract was placed 2 months before the expiry of the rate contract resulting in procuring computers of one year old specifications. • Contract copy for purchase of Microsoft Office 2007 not available in the file. • Monthly progress report on 3rd Party evaluation of civil works does not provide number of works completed in time, cost savings achieved or other parameters like time / cost overruns and the area requires attention from MPSP or the district engineer.

  11. Key Observations • Contract signed, date of invoice and date of cheque are on the same day. • Completed procurement cycle within one day. • Quotations from 2 firms are on the same hand writing . • Followed Zilla Parishad Procurement Procedure instead of FM&P Manual. • Hearing aid procured under single tender basis. • Delay in delivery of green boards since December 2008. • In the absence of any stipulation in the contract agreement 60% payment was released to the external auditor.

  12. Key Observations • UTTAR PRADESH • Procured items not taken into fixed asset register and not mentioned the warranty as comprehensive. • Minor error in the purchase order/invoice amount and amount paid. • Failure to mature the procurement process, resulted in non-availability of 3rd Party consultants for civil works quality. • Entire procurement cycle was completed from 6 March 2010 till 31st March 2010 but the goods received on 1st May 2010. • Single tender adopted for construction of composite schools (` 35.62 lakh).

  13. Key Observations • Invoice dated 31st March 2010 but delivered on 27th April 2010 resulting in delay in delivery. • Entire procurement cycle was completed with 2 days. • Stipulated unrealistic delivery period. • Not stipulated warranty terms in PO. • Liquidated damages not charged though stipulated in PO. • Invoice date prior to the placement of PO and payment. • Tower Server not installed since its receipt entails to under utilization for the procured goods. • Procured goods were not traced in the location (0.8 KVA and 1 KVA UPS)

  14. Key Observations • Cheques were drawn and kept ready before the placement of purchase order. • 50% payment was made upfront for maintenance of computers. • Hand-pumps to various schools procured on single tender basis. • Confirmation on the receipt of hand pumps from BRC not available in file. • Substantial delay in delivery and payment • Computer purchased received on 28-5-2010 but not found installed during the site visit. • Mismatch between specified in PO and supplied. Upon noticing and communicating, the items were found not replaced (based on site inspection)

  15. Key Observations • Installation of Server not done and however, certified by the computer operator for making payment • Procurement procedure followed for primary kit was not in line with Para 115.20, 21 and 22 • Stringent penal action proposed in the tender document • Quality assurance committee commented on the quality of text books, however, no deduction recommended. • Delay in delivery and completion of text books • Delay in payment of text books

  16. Thank You

More Related