Sediment Quality Assessment and Management Framework for Dam Removal Projects

Sediment Quality Assessment and Management Framework for Dam Removal Projects. Brian Graber & Karen Pelto Riverways Program, Massachusetts Fish & Game Joseph Rathbun Water Bureau, Michigan Dept. of Environmental Quality James Turek NOAA Restoration Center Laura Wildman American Rivers.

yaron
Download Presentation

Sediment Quality Assessment and Management Framework for Dam Removal Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sediment Quality Assessment and Management Framework for Dam Removal Projects Brian Graber & Karen Pelto Riverways Program, Massachusetts Fish & Game Joseph Rathbun Water Bureau, Michigan Dept. of Environmental Quality James Turek NOAA Restoration Center Laura Wildman American Rivers

  2. Basic Concepts: Reservoirs are Sediment Traps • Many trap 95 % of the sediment that enters them from upstream • Large sediment particles typically form deltas at upstream end • Small sediment particles typically transported farther into reservoir • Many contaminants typically bind to small particles

  3. Basic Concepts: Issues with Contaminated Sediment • Direct toxicity to organisms • Acute • Chronic • Bioaccumulation in organisms • Alter benthic community • Contaminate overlying water • Affect disposal of dredged material

  4. Initial screening indicates sediment contamination likely Reconnaissance and/or definitive survey SQC not exceeded SQC exceeded Analyze transport capacity & downstream sensitivity Not bioavailable Bioavailable Low transport capacity High transport capacity (Optional) Sediment Management Framework Sediment Assessment Framework

  5. Initial Landscape-Level Screening • Screen impoundment sediment quality based on landscape-level GIS information • Screening can flag an impoundment, watershed, or region for likely contaminants

  6. Predictive Model - RISQA • Regional • Impounded • Sediment • Quality • Assessment • Working with USGS • Probabilistic model to estimate: • Sediment quantity • Trace elements • Organic contaminants

  7. Developing and Validating RISQA • Compile existing data on sediment quality and quantity in impoundments • Field assess volume and quality of sediment in selected impoundments • Develop and validate a GIS-based model for predicting sediment quantity and quality based on basin characteristics

  8. *preliminary data* HazardImpoundmentPEC exceedances Sig. PXZ-001 none Sig. D2Z-008 PAH High UXZ-001 Cd, Cu, Pb, Cr Sig. NUZ-001 Cu Low HKZ-001 none none LVZ-001 Cr Low A2Z-001 none Low PTZ-001 Pb, PAH, PCB Sig. FTZ-001 Cd, Pb Sig. AJZ-001 DDE Combine dam hazard classification with contaminant assessment?

  9. Preliminary Modeling Results Preliminary regression analyses indicate that sediment contamination variability may be best explained by: • Percent impervious area • Number of point sources (NPDES, 21E, underground tanks, etc.) Additional impoundments are currently being assessed to validate the model

  10. Preferred Survey Design Process • Establish study objectives, evaluate existing data, etc. • Conduct reconnaissancesurvey • Refine study objectives - Choose minimum number of stations that are representative of study area • Conduct definitive survey

  11. Reconnaissance Survey • Objectives • Sampling access • Sample collectability • Qualitatively assess nature and extent of deposits • Quantitatively collect a small number of (silt) sediment quality samples • Equipment • Probing rod or tube • Small grab or core sampler • GPS

  12. Reconn. Survey – Mud Music ♫ Use hollow metal tube to identify surface sediment type: • Rock = bounce & clang • Clay = bounce & silent • Gravel = crunch • Silt = silent, penetration • Sand = silent, no penetration Reconn. sample from silt portion

  13. Moving from Reconn Survey to Definitive Survey Combine: • Reconn survey info • Regulatory guidelines/requirements • State specific • Watershed screening information (due diligence) • Best professional judgment To determine if additional assessment is needed ex. headwaters; run-of-river; gravel

  14. Definitive Survey • Objective • Quantitatively establish magnitude and extent of contamination • Equipment • Grab or core samplers • GPS Largely the same as reconn…

  15. Definitive Survey Sampling Design • How many samples will be collected • Where samples will be collected • How samples will be collected

  16. Sampling Design – How Many? • Most subjective part of survey design • Best Professional Judgment and regulatory guidelines • Minimum 50-ft diameter “hot spots”? • $$$$ (affects sampling resolution) • Elipgrid-PC software • Computes probability of locating “hot spots” • Based on total area, grid spacing, and potential hot spot size, shape, orientation • Can use to determine number of samples

  17. Sampling Design – Where? • Objective of the study • Cost-effectiveness • Use Elipgrid-PC • Sediment patterns

  18. Simple Random Sampling Dam

  19. Systematic Grid Sampling Dam

  20. Subjective Sampling Dam Outfall

  21. Stratified Random Sampling Dam Gravel Bar Silt Bar

  22. Sample Collection: Grab Sampling • More “recent” sediments (?) • Mixed, mobile surface layer • (grab 2 – 24 L) • “Biologically active” zone • Upper 10 cm or so Ponar Sampler

  23. Sample Collection: Core Sampling • Recent to older sediment • Stratified, less mobile deposits • important if mobilized during removal • Hand corers • Cores = a few feet long, 2” diameter • Shallow water • Gravity corers, piston corers, etc. • Cores < 5’ long • Deep water • Vibrocorers • Cores = up to 20’ long, 4” diameter • Deep water (> 1,000’) • Less disruption of sediment column • Challenges in gravel, clay

  24. Sample Analysis - Chemical • Often only testing done – least expensive • Methods well-established • Common analytes = metals, PCBs, PAHs

  25. Sediment Analysis – Toxicity • Done less often than chemical testing • greater expense • requires larger sample • Why do toxicity testing? • Integrates effects • Uses important food chain organisms • Direct proof of effects No effect = no pollution (?) Midge larvae Amphipod

  26. Data Interpretation:Sediment Quality Criteria Uses: • Evaluate sediment quality • Establish cleanup objectives • Assess suitability for disposal • Assess suitability for natural erosion & deposition Agree to at start of project

  27. Chemical Concentration SQC • Tied to biological effects • Cu > X ppm = mortality in mayflies • Usually tied to toxicity rather than bioaccumulation or changes in community structure or human health • More often guidelines than regulations • vary state to state

  28. Database Chemical SQC PEC = probable effects concentration (above which effects are probable) TEC = threshold effects concentration (below which effects rarely observed) Presumed Toxic PEC Possibly Toxic Increasing Concentration TEC Presumed Nontoxic

  29. Low transport capacity and/or high d/s sensitivity High transport capacity and/or low d/s sensitivity Not bioavailable Bioavailable (Optional) Natural erosion & deposition Staged dam removal Cap or isolate Partial sediment removal Full sediment removal Sediment Management Framework

  30. Complete Dam Removal & Natural Erosion & Deposition Issue: demonstrate transport & deposition will not: • Cause long-term adverse physical habitat changes downstream or upstream • Fill pools, bury riffles, etc. downstream • Upstream channel incision • Increase bioavailability (exposure/mobilization) of contaminants

  31. Staged Dam Removal & Natural Erosion & Deposition Issues: • Assess engineering suitability of dam for staged removal • Assess probability, magnitude, impacts of higher, “pulsed” water flows and sediment loads on downstream geomorphology and ecology • (Plus issues for complete dam removal)

  32. On-Site Isolation or Capping Issue: demonstrate that: • Capping will reduce contaminant availability to aquatic and terrestrial ecosystems, and humans • Capping won’t disrupt remaining ecosystem • Decrease riparian zone, wetlands, bottomlands, etc.

  33. Partial Removal of Hot Spots Tasks: • Locate hot spots • Remove & dispose of sediment • In the “dry” or “wet” • Demonstrate that remaining sediment is nontoxic • Post-remediation monitoring

  34. Sediment Removal – “Wet” & “Dry” (HRC, Inc.) (ECT, Inc.)

  35. Full Removal of All Sediment Tasks: • Identify extent of contaminated sediment, in3D • Characterize degree of contamination, for disposal decisions • Assess potential disturbance of original channel bed • Remove & dispose • Post-remediation monitoring

  36. Initial screening indicates sediment contamination likely Reconnaissance and/or definitive survey SQC not exceeded SQC exceeded Analyze transport capacity & downstream sensitivity Not bioavailable Bioavailable Low transport capacity High transport capacity (Optional) Sediment Management Framework Sediment Quality and Management Options

  37. Contaminated Sediment = Run Away? • Dams as a long-term sediment and contaminant management plan? • Reservoir = contaminant “time bomb”

  38. For more information: • Brian Graber, brian.graber@state.ma.us • Joseph Rathbun, rathbunj@michigan.gov