EDW Project Scope and Update February 5, 2007. Topics. Overview Process EDW Scope and Progress Questions/Comments. MIS – High Level. Protocol/Other Binding Documents. EDW/ CDW. Source Systems. Current Day Data. Mkt Info System. UI. API. Screen Display. Data Extract.
E N D
EDW Project Scopeand UpdateFebruary 5, 2007 http://nodal.ercot.com 1
Topics • Overview • Process • EDW Scope and Progress • Questions/Comments http://nodal.ercot.com 2
MIS – High Level Protocol/Other Binding Documents EDW/ CDW Source Systems Current Day Data Mkt Info System UI API Screen Display Data Extract Formatted Report Data Extract User System Manual http://nodal.ercot.com 3
EDW – Where We Fit Notifications Extracts EDW Protocols Nodal/Zonal Nodal Data Services Master List Business/Market Reqs Market Guides Reports Current Day Reports Replication Data Marts Alerts Lodestar Parser Source System Reports DMT Market Documentation http://nodal.ercot.com 4
The Process We Follow Step 1: Ensure protocol compliance and traceability (NDSML) Step 2: Define scope of reports and extracts for EDW and CDR (NDSML) Step 3: Prioritize reports and extracts (EDS Releases) Step 4: Develop business requirements for each report or extract (Requirements template) Step 5: Develop report or extract Step 6: Review with business for comments Step 7: Post to Nodal Readiness Center for MP review Step 8: Revise as needed to support comments, changes in source systems, and data availability http://nodal.ercot.com 5
EDW Summary Releases • EDW 1A – 1/31/08 (EDW DEV) • Status: Completed as DRAFT and reviewed by business owners • RSS not in place; missing SE data in EDS, PI data sporadic • DRAFT State Estimator Reports • Voltage Residuals vs. Telemetry for Critical Buses (NP3-582-ER) • Electrical Buses not meeting Telemetry Accuracy Requirements (NP3-363-ER) • MW Residuals vs. RTCA Base Case for Critical Transmission Elements (NP3-579-ER) • MW Residuals vs. Telemetry for Major Transmission Elements (NP3-581-ER) • MW Residuals vs. Telemetry for Critical Transmission Elements (NP3-580-ER) • State Estimator Convergence (NP3-578-ER) • DRAFT State Estimator Extract • State Estimator Statistics Extract – SESTATS_EXTRACT • CRR Replication: CRR FAT to EDW DEV • CMM Replication from CMM FAT to EDW DEV • DRAFT reports posted to Readiness Center: • http://nodal.ercot.com/readiness/reports/index.html http://nodal.ercot.com 6
EDW Summary Releases • EDW 1B – 3/14/08 (EDW FAT) • Status: Started on 1/28/08; on schedule • Dependent on RSS boxes available to EDW by 2/7/08 • State Estimator Reports • Voltage Residuals vs. Telemetry for Critical Buses • MW Residuals vs. RTCA Base Case for Critical Transmission Elements • MW Residuals vs. Telemetry for Major Transmission Elements • MW Residuals vs. Telemetry for Critical Transmission Elements • State Estimator Convergence • State Estimator: Extract • State Estimator Statistics Extract – SESTATS_EXTRACT • Telemetry Reports • Critical Points Violating Quarterly Availability Standards (S8) • ICCP Link Availability Statistics (S8) • Monthly Market Participant Real Time Availability Statistics (S8) • QSE ICCP Link Availability* (S8) • TSP ICCP Link Availability* (S8) • Quarterly Point Availability Statistics (S8) • MMS Reports • Report: Security Violations & Binding Transmission Constraints • Replication • Outage Scheduler Replication: OS FAT to EDW DEV (Source needed by 2/11) • CRR Replication: CRR EDS to EDW FAT (CRR EDS needed by 2/11) • CMM Replication: CMM ITEST to EDW FAT (CMM ITEST needed by 2/15) • MMS Replication: MMS FAT to EDW DEV • EMS Replication: EMS EDW to EDW PTEST * Assumes MP distinction can be made based on EMS data from SCADA module http://nodal.ercot.com 7
EDW Summary Releases • EDW 1C – 3/31/08 • Dimensional Maintenance Tool (DMT) in EDW FAT • ICCP Link Outage Scheduler • Critical/Significant Points Mgmt • Historical Congestion Elements • Critical Buses • Major Transmission Elements • Replication • Siebel replication: Siebel ITEST to EDW DEV • Additional EMS Reports • Prevention of Temperature Rating Adjustment (NP3-430-ER) • Resource Capacity Factors (NP4-528-ER) • Changes To RUC Committed Resources (NP5-108-ER) • Dynamic Rating Report (NP6-216-ER) • Total Amount of Regulation Service (NP6-654-ER) • Actual Resource Output (SYS-12) • Commercially Significant Constraints – Daily (SYS-128) http://nodal.ercot.com 8
EDW Summary Releases • EDW 2A – 5/14/08 (EDW DEV) • Status: Business requirements due 3/1/08 • COMS Shadow Settlements Extracts • Day Ahead Market Settlements & Billing Extract (NP12 -177) • Day Ahead Consolidated Operating day Extract (NP12-743 ) • Real Time Market Consolidated Operating Day Extract (NP12 – 747) • Real Time Market Operating Day Extract (NP12 – 749) • Public Reference Data Extract (ZP12 – 465) • Settlement Input Data Extract (NP12 – 753) • Extract Scheduler • Lodestar Parser • Lodestar Replication • EDW 2B – 6/14/08 (EDW ITEST) • Same as in DEV above http://nodal.ercot.com 9
EDW Summary Releases • EDW 3.0 – 8/31/08 (ITEST) • Status: Not started • All Non-Shadow Settlements Extracts, Reports & Web Services Reports • Extracts - COMS • CRR Balancing Account Extract • Late Fee Extract (combining NP9 – 308 and NP9 – 565) • ESI ID Service History & Usage Extract (ZP12 – 245, 246, 247) • Recorder Extract (ZP11 – 489) • Resource Identifier Extract (ZP11 – 532, 535) • Market Participant Dispute Extract ( ZP9 – 515) • Settlement Calendar Extract (NP9 – 598) • Settlement Input Data Extract (NP12 – 753) • CRR Auction Revenue Distribution (CARD) Extract (NP9 - 97) • Reports – Outage Scheduler • Resource Outage Statistics on Planned vs. Actual • Transmission Outage Statistics on Planned vs. Actual • Web Services • Provide all ESI ID extract records (COMS - 438) • Provide data aggregation records (COMS - 440) • Provide ESI ID extract records for logical keys (COMS - 442) • Provide ESI IDs where IDR usage data not loaded for a trade date (COMS - 444) • Provide IDR usage data for a trade date (COMS - 447) • Provide ESIID account records (COMS 441) • Provide public data extract (COMS 452) • Provide CMZONE assignments for a trade date (COMS - 439) • Extract Scheduler http://nodal.ercot.com 10
EDW Summary Releases • EDW 4: 8/31/08 (tentative) • Status: Not started, pending NPRR review and resolution of when/what needed • EDW MMS Section 8 • COP Report (S8) • RUC Report (S8) • EDW OS Reports Section 8 • Outage Schedule Report (S8) • Outage Scheduler Metrics (S8) • Other Section 8 Reports • CPS1, CPS2, DCS Reports (NP8-143) • Disturbance Performance Report (NP8-212) • Non-Spin Performance Report (NP8-383) • PDC Unit Trip Report (NP8-418) • Provided Regulation (NP8-501) • Historic Non-Spin Availability (NP8-504) • Voltage and Reactive Control Performance Metrics (4 reports) (NP8-511) • Blocked Governor Response Report (NP8-514) • Controllable Load Qualification Test (NP8-517) • Responsive Reserve Performance Report (NP8-541) • Responsive Reserve Availability Report (NP8-542) • Unit Performance Report (NP8-691) http://nodal.ercot.com 11
Questions/Comments http://nodal.ercot.com 12