1 / 3

PM 592 Task A was to have costFocus Dreams/tutorialoutletdotcom

FOR MORE CLASSES VISIT<br>www.tutorialoutlet.com<br><br><br>$110,000.<br>Task D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It<br>was estimated to cost $450,000 when finished. It is approximately 55% complete. Using this data, calculate the following. 1. What are the PV, EV, and AC for each of the activities and the complete project? (5 points)<br>PV AC EV Task<br>

year2k38
Download Presentation

PM 592 Task A was to have costFocus Dreams/tutorialoutletdotcom

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PM 592 Task A was to have costFocus Dreams/tutorialoutletdotcom FOR MORE CLASSES VISIT www.tutorialoutlet.com

  2. PM 592 Task A was to have costFocus Dreams/tutorialoutletdotcom PM 592 Task A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule FOR MORE CLASSES VISIT www.tutorialoutlet.com $110,000.Task D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. Itwas estimated to cost $450,000 when finished. It is approximately 55% complete. Using this data, calculate the following. 1. What are the PV, EV, and AC for each of the activities and the complete project? (5 points)

  3. PM 592 Task A was to have costFocus Dreams/tutorialoutletdotcom

More Related