FOR MORE CLASSES VISIT<br>www.tutorialoutlet.com<br><br><br>$110,000.<br>Task D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It<br>was estimated to cost $450,000 when finished. It is approximately 55% complete. Using this data, calculate the following. 1. What are the PV, EV, and AC for each of the activities and the complete project? (5 points)<br>PV AC EV Task<br>
E N D
PM 592 Task A was to have costFocus Dreams/tutorialoutletdotcom FOR MORE CLASSES VISIT www.tutorialoutlet.com
PM 592 Task A was to have costFocus Dreams/tutorialoutletdotcom PM 592 Task A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule FOR MORE CLASSES VISIT www.tutorialoutlet.com $110,000.Task D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. Itwas estimated to cost $450,000 when finished. It is approximately 55% complete. Using this data, calculate the following. 1. What are the PV, EV, and AC for each of the activities and the complete project? (5 points)
PM 592 Task A was to have costFocus Dreams/tutorialoutletdotcom