ABT LHC upgrades in the 2013 Long Shutdown Electronics & Controls

ABT LHC upgrades in the 2013 Long Shutdown Electronics & Controls. Disclaimer. Available resources (P+M) not taken into account No priority in the list Assumption of a full re-commissioning before restart (without & with beam). All. Software maintenance SIEMENS (PLC & Supervision)

yosef
Download Presentation

ABT LHC upgrades in the 2013 Long Shutdown Electronics & Controls

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ABT LHC upgrades in the 2013 Long ShutdownElectronics & Controls

  2. Disclaimer • Available resources (P+M) not taken into account • No priority in the list • Assumption of a full re-commissioning before restart (without & with beam)

  3. All • Software maintenance • SIEMENS (PLC & Supervision) • Embedded software • Application (JAVA) • Migration to FESA 3 • Migration to LINUX (CPU upgrade)

  4. MKI • Increase remote diagnostic (Shot-by-shot, IPOC…) • Redesign FIB to reject CIBO noise • Deploy new ACOND algorithm • Implement thermal protection in RCPS (discharge resistor) • Implement over-voltage interlock in RCPS • Validate RCPS surveillance

  5. MKI (cont.) • Implement thermal measurement on RCPS capacitors • Optimise TMR signal acquisitions (reduce cable losses…)

  6. LBDS • Recalibration of major components (power supplies, dividers, BEA’s…) • Optimisation of PROFIBUS frame (increase data transmission capabilities) • Implement low-level PLC diagnostic functionalities • Deploy TSU-V3 (hardware, firmware + interface board) • Add PTU output currents to MKD generator IPOC

  7. LBDS (cont.) • Install & commission Electronics & Controls for additional MKB generators • Implement GTO switch turn-on delay compensation (variable digital delay) for operation at fixed triggering voltage • Upgrade PTC firmware for PTM triggering current surveillance (…if less discrepancy between trigger transformer)

  8. LBDS (cont.) • Upgrade IPOC systems triggering logic • Maintain PTU’s (power supplies, capacitor, dust…) • Reduce triggering cable inductance (tri-axial to coxial) • Connect IPOC results to low level interlock logic (MKD Rogowski& Pearson, MKD generators, TSU) • Deploy local console in MKB areas

  9. MKQAc • Upgrade AC dipole electrical distribution • Integrate AC dipole control within MKQA control • Adapt AC dipole functionality (longer flat-top)

  10. TCDQ • Separate electrical distribution from LBDS • Split PRS & MDC in 2 different PLC’s • Replace LVDT with a second potentiometer • Consolidate operational performances for small displacements • Tolerance & resolution • Compensation of mechanical clearances • Positioning PID (torque & brake control)