350 likes | 434 Views
MODIFICATIONS TO A PRA MODEL TO ADDRESS MULTIPLE SPURIOUS OPERATIONS (MSOs). Presented at the ANS PSA 2008 Topical Meeting September 7–11, 2008 Knoxville, Tennessee. Richard Anoba, Anoba Consulting Services, LLC David Miskiewicz , Progress Energy Carolinas, Inc. Introduction.
E N D
MODIFICATIONS TO A PRA MODEL TO ADDRESS MULTIPLE SPURIOUS OPERATIONS (MSOs) .
Presented at the ANS PSA 2008 Topical MeetingSeptember 7–11, 2008Knoxville, Tennessee
Richard Anoba, Anoba Consulting Services, LLCDavid Miskiewicz, Progress Energy Carolinas, Inc
Introduction • Increasing use of PRAs to develop Fire PRA Models for NFPA-805 Application • Increasing demands to address fire-induced multiple spurious operations (MSOs)
What is a MSO? • A MSO is unique to fire initiating events such that it involve fire-induced failure of multiple electric-powered components that lead to undesired end states • Spurious closure/opening of MOVs, AOVs, SOVs, etc due to fire-induced hot short. • Spurious starting/stopping of pumps, etc due to fire-induced hot short
How do we model MSOs? • NUREG/CR-6850 • ANS Fire PRA Standard • Expert Panel Reviews • Fire Safe Shutdown Analysis (Appendix R) • No specific “how to” guidance
Modeling Challenges • PRA model alone will not capture all possible MSOs • Apendix R captures single spurious operation • Expert panel can capture additional MSOs based on Appendix R safe shutdown functions and systems
Modeling Challenges • Requires commprehensive review of all inputs/guidance plus creativity of PRA analyst • The modeling of MSOs in the PRA model presents some unique issues that the PRA analysts must deal with • Fault tree is a static model, while a fire scenario is time-dependent
Modeling Challenges • The duration of a hot short event that causes the MSO might be on the order of 10 to 20 minutes after which the fire-induced fault becomes a short-to-ground • At this point power is removed from the component and the hot short event is terminated.
Modeling Challenges • Competing MSO failure modes for the same component may be mutually exclusive • Alternatively, MSO failure modes that have to occur later in time may be invalid
NUREG/CR-6850 Component Selection (Key MSO Steps) • The NFPA-805 project typically includes a task to develop the component list to be considered for inclusion into the Fire PRA model using NUREG/CR-6850 • Identify electrically dependent components in the PRA model and in Appendix R.
NUREG/CR-6850 Component Selection (Key MSO Steps) • Reconciliation of differences between the Appendix R Analysis and the PRA • Addition of components whose potential spurious actuations (considering multiples) could challenge the event mitigation capability.
NUREG/CR-6850 Component Selection (Key MSO Steps) • Addition of instrumentation important to human response • Inclusion of components whose failure, by itself, could cause high consequence events as defined in the NUREG/CR-6850 • Addition of components identified by the expert panel review team
Expert Panel Reviews • Focus on Appendix R or Safe Shutdown functions and systems (2 Spurious operations) • Many identified MSOs are also applicable to Fire PRA • PRA analyst needs to expand focus to PRA functions and systems
A - Loss of Reactivity Control • 1- Boron Dilution • 2- Uncontrolled Cooldown
B - Loss of Reactor Coolant System (RCS) Inventory Control • 1- Reactor Coolant Pump Seal LOCA • 2- Stuck Open Pressurizer PORV • 3- Spurious Opening of Head/High Point Vents • 4- Spurious Opening of Letdown Line • 5- Diversion flowpaths for RWST inventory • 6- Pump dead head
C- Excessive RCS Injection • 1- Spurious HPI injection in excess of letdown capability with failure of Pressurizer PORV
D- Loss of RCS Pressure Control • 1- Spurious Auxiliary Pressurizer Spray • 2- Spurious Pressurizer Heater Actuation • 3- Spurious Start of RCP with subsequent pump heat • 4- Spurious normal Pressurizer spray with RCPs running
E- RCS Overcooling • 1- Spurious Turbine Bypass Valve actuation • 2- Failure of MSIVs to close with spurious opening of downstream condenser/atmospheric dump valves • 3- Spurious opening of MSIV bypass valve • 4- Failure to isolate SG Blowdown Valves
F- Loss of Decay Heat Removal • 1- Spurious isolation of MFW flow path • 2- Spurious start of AFW system
G- Loss of Support System • 1- Loss of Electrical Power • 2- Loss of Component Cooling Water System • 3- Loss of Salt Water Cooling System • 4- Loss of HVAC • 5- Loss of Instrument Air
Characterization and Evaluation of MSOs • A- MSO already addressed in the PRA • B- MSO from Appendix R excluded since PRA function not impacted • C- New MSO from various steps in the component selection task • D - New MSO from Appendix R • .
Characterization and Evaluation of MSOs • E - New MSO from expert panel review • F - MSO from Appendix R and incorporated into the PRA
Spurious Opening of Reactor Vessel or Pressurizer Vent Valves Causes Small LOCA
Spurious Opening of SG Blowdown Valves Causes Uncontrolled Secondary Depressurization
Summary • Although, the PRA already addresses many of the MSO issues, there remain a handful of issues that require model modification • Extensive modifications to the PRA model may be required to adequately address MSO
Summary • Time-dependent nature of a fire scenario can cause mutually exclusive failure mode combinations and/or invalid failure modes. These need to be addressed. • New failure scenarios may require additional supporting deterministic analyses