2008 KYTC/KAHC Information Exchange Meeting

2008 KYTC/KAHC Information Exchange Meeting. Lexington, KY – March 3 rd Bowling Green, KY – March 10 th. Material Spec. Changes / Structural Branch. Concrete Pavement Opening Strength Concrete Plants for Large Projects Coring Concrete Pavement for Thickness Pavement Drainage Blankets

yves
Download Presentation

2008 KYTC/KAHC Information Exchange Meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2008 KYTC/KAHCInformation Exchange Meeting Lexington, KY – March 3rd Bowling Green, KY – March 10th

  2. Material Spec. Changes / Structural Branch • Concrete Pavement Opening Strength • Concrete Plants for Large Projects • Coring Concrete Pavement for Thickness • Pavement Drainage Blankets • Striping Retroreflectivity • Cold Weather Concrete

  3. Concrete Pavement Opening Strength • Supplemental Spec Change July 22, 2005 • Performed a Nationwide Survey of DOT’s • DOT’s Average 3000 psi for Opening • KY Changed Opening Strength to 3000 psi • Acceptance Based on 3500 psi at the Required Age

  4. Concrete Plants for Large Projects • Supplemental Spec Change July 22, 2005 • Large Projects are ≥250 Cubic Yards • Total Cubic Yardage is for ALL Concrete on the Contract • Concrete Bid Items (example - Concrete Class A) • Incidental Concrete (example – Guardrail End Treatments) • Plants Must be on the List of Approved Materials and Comply with KM 64-323

  5. Coring Concrete Pavement for Thickness • Supplemental Spec Change August 11, 2006 • Contractor Responsible for Performing Coring in Accordance with KM 64-309

  6. Pavement Drainage Blankets • New Change for 2008 Specifications • No Untreated Drainage Blankets • Drainage Blankets will have to be Asphalt or Cement Treated • Type II (Asphalt Treated) • Type III (Cement Treated) • Constructability and Performance Issues

  7. Striping Retroreflectivity • New Changes for 2008 Specifications • Raised the Bar on Retro Acceptance for Permanent Striping, Durable Markings, and Thermo for Intersections • Based on Determination that Higher Numbers Were Easily Achieved and Most Contractors Received Maximum Bonus on District-Wide Projects • All Yellow Thermo Must be Nonleaded • Intend to Set Contracts Up with Temporary and Permanent Striping

  8. Cold Weather Concrete • Future Changes for Specifications • Plan • Temperature Recordings • Temperature Controls • Placement • Curing • ACI 306R, ACI 306.1

  9. Questions or Comments? Ross Mills Division of Materials (502) 564-3160 ross.mills@ky.gov