1 / 13

Presentation On:

Presentation On:. By Engr. M. Mazhar-ul-Islam. SALIENT ISSUES IN CONTRACT ADMINITRATION. Convener, PEC Act & Bye-laws Committee. Procurement & Contract. Management means organization and co-ordination of activities Procurement is a process of buying and selling the products

yves
Download Presentation

Presentation On:

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presentation On: ByEngr. M. Mazhar-ul-Islam SALIENT ISSUES IN CONTRACT ADMINITRATION Convener, PEC Act & Bye-laws Committee

  2. Procurement & Contract • Management means organization and co-ordination of activities • Procurement is a process of buying and selling the products • Administration generally during currency of contract • More particularly during supervision stage • Procurement is realized through a Contract • A contract is an agreement enforceable by law • Essentials of a valid contract: (a) competent to contract (b) free consent (c) lawful considerations (d) lawful objects

  3. Contract stages • Administrative activities for handling of contracts: • Invitation to Bid • Bid Evaluation • Award of Contract • Implementation of Contract • Measurement of completed work • Computation of payments • Modifications in the Contract etc.

  4. What is Engineering Contract • Engineering Contracts – for goods, works and services defined under Section-2(XXV) of PEC Act 1976 for Professional Engineering Works • Agreement = Proposal + Acceptance • Bidding/Tendering is to seek proposal • Principles conforms to Contract Act 1872 • All contracts are agreements but all agreements are not contracts

  5. Typeof Contracting • Conventional Contract • EPC contract • Design and Build Contract • Turn Key Contract • BOT Contract • Fast Track Contract • Cost Plus Fixed Fee Contract

  6. Pakistani Laws on Contract • The Contract Act, 1872 • The Arbitration Act, 1940 • The Limitation Act, 1908 • The Specific Relief Act, 1877 • The Partnership Act, 1932 • The Stamp Act, 1899 • Pakistan Environmental Protection Act, 1997 • The Registration Act, 1908 • Income Tax Laws • Law of Conveyancing • Land Acquisition Act, 1894 • Labor Laws

  7. AWARD OF CONTRACT • Award to lowest evaluated responsive bidder • Conditional acceptance of NOCA • Status of NOCA • No agreement without performance security • Agreement to be signed within 14+14 days • Agreement not to change bidding provisions • Amendment in Contract subject to the limitations

  8. Variation of Works • Variation in quality and quantity • Adjustment due to measurement is not a variation • Variation to be effected with issuance of variation order • V.O to be issued by Engineer with prior concurrence of the Employer • Variation exceeding 15% needs negotiated settlement • No limitations in adjustment of price for V.O

  9. Extension of Time • Original Schedule should be measured and realistic • Unrealistic schedule leads to poor quality and non-performance of Contract • Right-of-Way, Non Payment etc. are generally Employer’s default • Contractor’s right to claim financial compensation, although conditional EOT is granted when Employer is in default • Deduction of liquidity damages for the delay attributable to the Contractor • Price Adjustment to continue, irrespective of delay or LDs

  10. Payment to Contractor • IPCs within 30 days after Joint Verification • Final Payment within 60 days after Joint Verification of Final Payment Certification • Price Adjustment due to increase or decrease of cost can be made concurrently or subsequently • Delayed Payment Compensation Kibor +2% and Libor +1% incase of local and foreign currencies

  11. Dispute Adjudication • In a contract a dispute is likely • Better documentation, less dispute • Engineer’s role in dispute resolution • Mode of Dispute Adjudication • Adjudicator • The Engineer • Dispute Board (DAB) • Amicable Settlement • Arbitration (Arbitration Act 1940) • PEC Rules of Consultation & Arbitration

  12. Miscellaneous issues • Blacklisting of Contractor • Only one amount, Secured advance or Financial assistance, can be granted • Insurance Guarantee in case of Bid Security and Performance Security • Insurance Security for Advance Payment Guarantee is at the option of the Employer

  13. Thankyou

More Related