1 / 14

Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review

12GeV Upgrade - Beam Transport. Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review. LINACs Michael Bevins May 17, 2007. Outline. Introduction & Scope Requirements & Specifications New/Modified Linac Elements/Girder Count Beam Transport Layouts

zamir
Download Presentation

Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 12GeV Upgrade - Beam Transport Injection, Linac, Extraction, & CorrectorsPreliminary Design and Safety Review LINACs Michael Bevins May 17, 2007

  2. Outline • Introduction & Scope • Requirements & Specifications • New/Modified Linac Elements/Girder Count • Beam Transport Layouts • Safety Considerations • Cost Estimates • Risk Assessment • Summary

  3. Introduction & Scope • The12GeV upgrade requires an additional ten cryomodules • Five in the north linac and five in the south • NEW modules are longer than the original CEBAF modules • Result: Warm region girders downstream of the new modules must be replaced with a new short girder • Like downstream of SL21 • 12GeV field strength requirements force us to replace two QB quads at the start of the linac with QCs • Songsheet level machine layouts, QB to QC mod, and the short warm region girder will be presented along with cost estimates • Only modified sections of the LINACs will be included in this presentation

  4. Requirements & Specifications • Alignment specs • Quads positioned to +/-0.5mm in x & y, +/- 1.0mm in z • Vacuum specs • Pre linac: (at MQB1L00 & 01) • Beam line partial pressure of hydrogen <10-6 torr • Total average pressure of all other constituents less than 5x10-7 torr • Warm region girders between cryomodules • UHV • Fabrication, welding, cleaning & handling, and leak checking specs still apply • 22631-S-001 Fabrication of Ultra-High Vacuum Equipment • 22632-S-001 Cleaning and Handling of U.H.V. Components • 22633-S-001 Welding Specification For U.H.V. Components • 22634-S-001 Helium Leak Test For U.H.V. Components • Note an update and modernization of our vacuum specs is underway

  5. New/Modified LinacElements/Girder Count • Elements in red are part of I&C WBS

  6. North Linac South Linac Beam Transport Layouts – N&S Linac • North Linac 1st Section • QB to QC change at MQB1L00 & 01 • N&S Linac Sections 3 & 4 • Add new modules in zones 22 through 25 • Replace warm region girders with new short girder

  7. Beam Transport Layouts – QB to QC change • MQB1L00 & MQB1L01 girder modifications • Replace QB quads with higher strength QCs • Shift MQB1L00 stand 4 inches upbeam to improve girder stability • Shift MQB1L01 upbeam 7.6cm from 12GeV dimad position View looking upbeam to MQB1L00 & 01 girders MQB1L00 MQB1L01

  8. Beam Transport Layouts – N&S Linac Layout of new modules & girders in linac DP station moved to end of linac Current Configuration (Zones 19 – 22) 12GeV Configuration (Zones 19 – 22) New module Replace module baseplates Current Configuration (Zones 23 – 26) 12GeV Configuration (Zones 23 – 26) Five New warm girders Four New modules

  9. Beam Transport Layouts – Warm Region Girders • Warm girder design reviewed in Oct 2004 • Prototyped and installed at SL21 • Designed to accommodate multiple combinations of cryomodule configurations • Quad, BPM, and alignment cartridges will be reused on new short girders H&V nested Air Core correctors over BPM Viewer & pump drop cross Quad New stand Existing baseplate New short warm region girder Old warm region girder

  10. Safety Considerations • Personnel Training • Jlab & sub-contractor • Radiation • Designated areas for containment and radiation survey of material that will be removed from the tunnel • Material handling • Provide provisions for lifting • Electrical Hazards • Package and support electronics, power leads and terminal blocks to control electrical hazards

  11. Cost Estimates – LINAC WBS Rollup WBS Elements I have covered today

  12. Cost Estimates - Highlighted WBS Girder & Stand Procurements * Warm girder qty includes one spare * Warm girder cost reviewed as part of Quad review on May 3rd 2007

  13. Risk Assessment • Technical - Low • Girders & Supports – very similar designs exist and are already proven • Warm region girder prototyped and installed at SL21 • Alignment - same as existing machine • Procurement Schedule - Low • No long-lead items identified • Cost – Low • Linac warm region girder recently prototyped • Good cost estimates for machined parts • Vendor & Jlab shop budgetary estimates

  14. Summary • Preliminary LINAC beam transport layouts, cost and installation estimates to support CEBAF at 12GeV are complete based on present scope • We are in a good position to support our DOE External Project Reviews this summer • We will continue to work closely with our friends throughout the lab (safety, CASA, installation, vacuum, alignment, RadCon, I&C, magnet measurement, operations, procurement & facilities) as we move forward • Detailed design will be completed to support assembly and installation schedules • We look forward to comments & recommendations from the committee

More Related