1 / 20

January 2009 SEMO Ice Storm Extreme Measures

January 2009 SEMO Ice Storm Extreme Measures. IEEE-PES St Louis Chapter Meeting June 18, 2010 Presented by David Wakeman Vice President, Energy Delivery AmerenUE. AmerenUE. Founded 1902 Serves 1.2 million electric customers and 127,000 natural gas customers

zena
Download Presentation

January 2009 SEMO Ice Storm Extreme Measures

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. January 2009 SEMO Ice StormExtreme Measures IEEE-PES St Louis Chapter Meeting June 18, 2010 Presented by David Wakeman Vice President, Energy Delivery AmerenUE

  2. AmerenUE • Founded 1902 • Serves 1.2 million electric customers and 127,000 natural gas customers • 21,000 square mile service territory

  3. Missouri Counties Served by AmerenUE That Were Affected • Cape Girardeau • Dunklin • Mississippi • New Madrid • Pemiscot • Scott • Stoddard

  4. January 2009 Ice Storm • Up to 5” of ice accumulation • Affected 36,500 customers • The entire “bootheel” area—including AmerenUE facilities—was seriously impacted • Over 4000 storm response personnel involved • Replaced 3800 poles and 1,440,000 ft of wire (273 miles) • All customers restored in 9 days

  5. Monday, January 26 • Quantum Weather predicts the possibility of ice storm in southern 1/3 of state • Mobilized contractor resources and Missouri Valley resources to SEMO south—approximately 250 personnel • Mobilized 3 storm trailers and 1 Mobile Command Center

  6. Tuesday, January 27Day 1 • At 4 a.m. only 800 customers out—Just the tip of the ICEberg • Major ice accumulation occurring throughout the day in SEMO south area • Decision made to move all AmerenUE resources to SEMO • Outage numbers climb throughout the day • Additional contractor resources procured • 650 linemen and 350 tree trimmers engaged by end of day

  7. Wednesday, January 28Day 2 • Ice continues to build—outage count over 36,000 in A.M. • 6 counties in Bootheel are essentially without power • Base Logistics called in A.M. to support logistics effort • Decision made to use Extensive Damage Recovery Method • SEMO south divided into 8 “restoration islands” • 1150 linemen and 450 tree trimmers engaged by end of day

  8. Thursday, January 29Day 3 • 2 helicopters employed to patrol 34 Kv system. Found 80 miles of line on the ground • Restoration plan is developed • Repair effort is focused on 34.5 Kv system to get substations re-energized • Massive amounts of devastation being reported • Established Field Logistics Team to help manage the logistics effort

  9. Restoration Progress • Sunday Feb 1 • Most 34.5 kV circuits restored • Released 1st Estimated Restoration Time • Monday Feb 2 • All 34.5 kV circuits restored (except Portageville 71—30 miles to rebuild) • Many distribution circuits restored • Tuesday Feb 3 • Customer outages under 10,000 to start day • Most customers restored by end of day • Wednesday Feb 4 • All customers restored by end of day • Work begins on Portageville 71

  10. Damage Summary • Virtually 100% of AmerenUE customers in 6 counties without power • 34 KV Sub-transmission System • 25 circuits out of service and requiring major repair • Portageville 71 (34kv) 30 miles long with 1 pole left standing • 35 distribution substations without power • 20 customer subs without power • Distribution System • 163 distribution circuits out of service

  11. SEMO Ice Storm 36,000 customers out Outage duration: 9 days Major Material Installed 3800 poles 7000 cross arms 700 transformers 1,440,000 ft of wire (273 miles) Sept 14, 2008 Wind Storm (Hurricane Ike) 161,000 customers out Outage duration: 4 days Major Material Installed 38 poles 295 cross arms 58 transformers 69,000 ft of wire Supply Chain IssuesComparison: SEMO Ice Storm vs. Sept 14, 2008 Storm (Hurricane Ike)

  12. Extreme Situations call for Extreme Measures • Logistics • Even if there would have been power, the existing logistics infrastructure in the region could not have handled the influx of resources • Restoration Methodology • Extensive Damage Recovery Method • Restoration Island Concept • Portageville 71 34.5 kV Circuit (completely destroyed)—deployed three 2MVA generators • Construction Standards—take advantage of the situation to re-build to “old” circuits to “new” standards

  13. Logistics • 15,500 Hotel Room Nights • 2300 Alternative Sleeping Arrangements—bunk trailers, dorms, etc • 76,000 meals • 1250+ loads of laundry • 44 buses

  14. Extensive Damage Recovery Method • Typical restoration method is to utilize Outage Analysis System to methodically restore orders from largest to smallest • Due to extreme amount of damage, decision was made to use the Extensive Damage Recovery Method • Subtransmission system was restored/rebuilt first • Feeders were then restored beginning at the substation and working to the last meter

  15. Restoration Islands • The service territory in southern SEMO was divided into 8 separate “Restoration Islands” • A management and support structure was developed for each Island and restoration resources were assigned based on specific need • Material Staging sites were established for each Island • Operational Conference Calls were held every afternoon to discuss issues and manage resource and material allocations

  16. Portageville 71 34.5 kV Circuit • 30 miles long with 1 pole left standing • Provided power to 2 towns • Decision was made early in the restoration process to rent large generators to provide temporary power to the 2 towns • When all other circuits had been restored, resources were assigned to rebuild the Portageville 71 circuit • Using 500 linemen, the 30 miles of 34.5 kV circuit was rebuilt in 3 ½ days

  17. Lessons Learned • It is impossible to prepare for every contingency • The ability to adapt is critical • Key Elements to Success • Logistics—personnel resources are limited by the available logistics infrastructure • Supply Chain—the flow of material into the affected area will affect restoration progress • Incident Command Structure—ensured an integrated, organized response • Restoration Work Islands—provided a manageable command and control structure in the field

  18. Questions or Comments?

More Related