60 likes | 164 Views
Sarasota Memorial Hospital Campus Improvement Plan. Neighborhood Advisory Council October 12, 2010 Construction Update. Project Phasing 1 & 2: Demolish CEP, Pre-Moves, New Garage Entry/Exit. . New CEP Completed. . Information Systems Complete – 5-Service. .
E N D
Sarasota Memorial Hospital Campus Improvement Plan Neighborhood Advisory Council October 12, 2010 Construction Update
Project Phasing 1 & 2: Demolish CEP, Pre-Moves, New Garage Entry/Exit New CEP Completed Information Systems Complete – 5-Service Central Receiving Complete – 1-Waldemere Wound Care – 2-Waldemere On-Call – 4-Central Observation Complete – 9-East Surgery/CS Vertical Expansion Interim Moves for Surgery Support & Pathology Temporary ECC Turn-around & Canopy Temporary Entry/Exit at Waldemere Garage Demolish Old CEP Temporary Main Entrance Canopy Legend: Green box means that portion will be completed in that phase. Beige box is ongoing. 2 2
Project Phasing 3 & 4: Temporary Drive, Complete Fall 2010 Legend: Green box means that portion will be completed in that phase. Beige box is ongoing. Wound Care – 2-Waldemere Temp Main Entry Turn-around& Canopy On-Call 3-East Surgery/CS Vertical Expansion Moves for Surgery Support & Pathology Complete Demolish Portion of Critical Care Tower Temporary ECC Turn-around & Canopy Complete Sitework & Temporary Drive 3 3
Project Phasing 5: Demolish Northeast Wing and Main Entry, Begin Bridge Legend: Green box means that portion will be completed in that phase. Beige box is ongoing. Temp Main Entry Turn-around & Canopy Demolish Northeast Tower Main Entry Canopy Structure for Bridge, Elevator & Stair Surgery/CS Vertical Expansion ECC Vestibule, Canopy and Drop-off Complete Sitework & Temporary Drive 4 4
Project Phasing 6: Patient Tower Foundations, South Connector Complete Winter 2010 - 2011 New Patient Tower Foundations Structure for Bridge, Elevator & Stair Surgery/CS Vertical Expansion & Connector to So. Garage Legend: Beige box is ongoing. 5 5
Project Phasing 7: Patient Tower Structure, Surgery / CS, New Patient Tower Structure Surgery/CS Vertical Expansion & Connector Complete Legend: Green box means that portion will be completed in that phase. Beige box is ongoing. 6 6