An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ZEN Project State of art of the project - Project closure Lucia Barberini Perugia, 11 September 2014

  2. AGENDA: • Progress Report 5 • Financial implementation • Project closure

  3. COMPONENT 1 Management and CoordinationLP responsible partner Sixth Semester Actions Financial/administrative management: • Financial management of the partnership, collection of reports, certificates, outputs, monitoring documents; • Drafting and presentation of 5th Progress Report (period 1st January – 30 June 2014) – to be submitted to JTS by 1st October 2014.

  4. COMPONENT 1 Management and CoordinationLP responsible partner: financial issues Sixth Semester Actions Financial management: • Budget reallocations in July 2014 to allow financial implementation • 5th Progress Report: good level of expenditures (98,79% of the forecasted) • Progress gap reduced # Some Partners are still on delay • Project financial implementation (30.06.2014) 76,34% (Dekpota data for PR4 and 5 missing and draft data for 2 Partners before FLC) • Criticalities: - Slight overspending of some Partners in some BL despite budget reallocation - External Expertise under Components 2 and 3 high amounts still to be paid out

  5. COMPONENT 1 : financial implementation and project administrative closure Sixth Semester Actions • Main activities will end by 30 September (Final Conference on 11th September): most part of expenditures must be paid out by 30.09.2014 • Only few amounts for residual activities (i.e. some dissemination costs, staff for administrative closure, First Level Controllers) can be paid out by 31.12.2014 • Following budget reallocation of July 2014, NO MORE BUDGET REALLOCATIONS WILL BE ALLOWED

  6. PROJECT CLOSURE RECOMMENDATIONS • The project end date is the cut-off date for all expenditure and activities. FLC MUST be done before 31 December 2014 in order their costs to be eligible. • The last progress report tends to be more extensive and we are required to double our efforts to make the report self-explanatory. • On-the spot checks are an obligation: a project cannot be closed if there is no reassurance that this requirement has been respected. • The Subsidy Contract obliges to keep the website accessible for further 5 years. It will continue to be a valuable tool for the dissemination of the project results.

  7. PROJECT CLOSURE RECOMMENDATIONS • A second level audit or a Commission audit can take place after the closure of the project and that the relevant documents need to be available. • According to the INTERREG IVC rules and to the ZEN PA documents and data about the part of the project for which each Partner is responsible MUST BE PRESERVED in a safe and orderly manner for a minimum period of 3 years after the payment of the final balance by the European Commission to the Interreg IVC programme. (i.e. 2019  2022) • It is important that all Partners indicate a person taking over the responsibility for the project. This is in the interest of all partners: the failure to provide requested information might lead to the exclusion of expenditure from the report and will delay the payment procedure.

  8. SUMMARY DEADLINES: • 1st October 2014: LP willsubmitto the JTS Progress Report 5 • 31st December 2014: Project end  All expenditures paid out • 15th January 2015: Send to LP expenditures list and Report on Activities for Progress Report 6 • 1st March 2015: Send to LP Certificates (Annex 5b and 6) for Progress Report 6 – Final • 1st April 2015: Submission to JTS of PR6 and Final Report