An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MICHIGAN TRAFFIC SIGNAL SUMMIT: REGIONAL COORDINATION IN ACTION TRB ANNUAL MEETING JANUARY 9, 2005 Gary Piotrowicz, PE, PTOE

  2. WHERE IT ALL BEGAN • MDOT management was getting pressure about poor signals, labeled as a forgotten priority • Oakland County Traffic Signal Summit • First meeting on August 9, 1999 • Included MDOT, RCOC, Cities, Consultants, Universities, and Traffic Improvement Assoc • Chaired by MDOT senior management • This showed MDOT was serious • Gave the Summit clout • Helped engage many people • Made things happen

  3. Development of Subcommittees • Discussions brought three primary issues to the top • Timely installation of signals • Clearance intervals • Signal timing and progression • Subcommittees were formed to address each issue • Chairs were assigned to each, volunteers signed up to participate

  4. TIMELY INSTALLATION OF TRAFFIC SIGNALS • Main Issue: Average new signal installation or left turn addition was taking 18 months • Causes: • Contracting • Power Company • Funding • Materials • Resolution: • Indefinite Delivery Contract

  5. INDEFINITE DELIVERY CONTRACT • Contractors bid line items, locations to be determined • Minimum number of intersections guaranteed • Power company can start work quicker • Funds obtained in advance • Stock pile of materials • Avg. installation time reduced to 5 months • Costs have only increased by 5%

  6. CLEARANCE INTERVALS • No statewide consistency • MDOT used a modified ITE formula for the yellow (4-5 sec). All reds used inconsistently (0.1 to 1 sec) • Evaluation looked at several different formulas • Concensus reached to use ITE formula for both yellow (3.5 to 5) and red (1 to 2.5).

  7. SIGNAL RETIMING • Nearly 900 non-SCATS signals • Never had a comprehensive re-timing • Cycle lengths, splits, and offsets • Peak periods • Clearance intervals • Dramatic volume changes • Pattern shifts • Many new signals along corridors • Minimal resources to maintain timings

  8. PUBLIC PARNTERS • City of Royal Oak • City of Pontiac • City of Ferndale • Wayne County • Road Commission of Macomb County • Michigan Department of Transportation • Road Commission for Oakland County • Traffic Improvement Association

  9. FUNDING AND PHASES • CMAQ funds were obtained through SEMCOG, MDOT, and RCOC • Estimated total project cost is $5.4 million • Phases 1 and 2 received money concurrently, completed in spring of 2004 • Phase 3 was funded later, currently about 2/3 complete

  10. DATA COLLECTION • Turning movement counts-AM,PM,Mid-day • 24-hour counts • Geometry and operations data • Traffic crashes/diagrams • Digital photos • GPS locations for GIS Mapping

  11. SAFETY COMPONENTS • Better signal timings….smoother flow…..safer roads • Clearance Intervals • Vehicle • Pedestrian • Crash analysis • Flash operations analysis

  12. PROJECTED BENEFITS • Benefit/Cost ratio of 80 to 1 • Decreased fuel consumption • Improved air quality • Reduction in traffic crashes • Politically friendly • Quicker implementation • Wealth of data

  13. STATUS OF TRAFFIC SIGNAL SUMMIT • Initially began in Oakland County, name updated to “Michigan Signal Summit” and others invited • First 3 subcommittees have sun-set and 3 new subcommittees have formed: • Evaluation • Near-term • Long-term

  14. Questions?