Email update from Gerry. I will sail with Eric instead of Stefan Physicals will be in Ollie Berka's hands by the end of this week Manual has been uploaded
E N D
Email update from Gerry • I will sail with Eric instead of Stefan • Physicals will be in Ollie Berka's hands by the end of this week • Manual has been uploaded • We want to test a different way to grab on to the T2P by lowering the ERS and then locking with the ERS in place instead of locking and then going for the grab. We may want to have the small version of the overshot that Tom has so we can do some quick testing onboard before operations begin. If this work we may reduce the risk of overextending the ERS to the point where it will not retrieve the T2P (similar to what happened in the last try at Sugarland). I can give you more details later on. • LDEO personnel planning on arriving in Curacao on May 26th; we have not purchased tickets but I do not see any problems on making this; we will buy tickets either at the end of this week or early next week.
26 April 2012 MDHDS Mtg • Equipment Delivery • What will be/has been delivered when • Detailed contents for all containers sent to TAMU • TAMU Shipping Plan • Complete manifest of all boxes shipped to Curacao (Gerry) – send to Tessa to post online
UT Delivered MDHDS • Tether assembly T2P • Two complete tools • Mobile pressure chamber Misc. • Tools, spare parts, etc. • Safety equipment (hard hats, gloves, etc.)
3. JR Field Test • JR Field Test • Tom: Status of testing plan for JR deployment • Status of medical paperwork (Bob) • Sample requests (whole core/shipboard plan) • Who gets on/off when and where? • What equipment is being hand-carried
UT Hand-Carry • Spare T2P parts still being made • Cables • New 5kpsi sensors • Laptops • Manuals • Deployment sheets
Manual Report by each contractor • Gerry: Review ERS Operations Manual Addendum and send Chris any edits