1 / 12

PEP-II B-Factory AIP

PEP-II B-Factory AIP. John Seeman SLAC Operations Review June 16, 2004. Past AIP funding. Accelerator Improvement Project (AIP) funding as proposed by the PEP-II staff over the years in order to increase the luminosity to remain competitive was about 7000 k$ per year.

fuller
Download Presentation

PEP-II B-Factory AIP

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PEP-II B-Factory AIP John Seeman SLAC Operations Review June 16, 2004

  2. Past AIP funding • Accelerator Improvement Project (AIP) funding as proposed by the PEP-II staff over the years in order to increase the luminosity to remain competitive was about 7000 k$ per year. • Actual AIP funding for past years: • FY99 = 3715 k$ • FY00 = 5800 k$ • FY01 = 6188 k$ • FY02 = 7100 k$ • FY03 = 3300 k$

  3. AIP funding has driven PEP-II luminosity increases!

  4. SLAC AIP Changes between Funding Plans • The SLAC Field Task Proposal (April 2004) used the following funding profile for AIP: FY05-FY09: 8M$, 8M$, 7M$, 6M$, 6M$. • The Lehman review proposed AIP funding profile for the “Base 2%” case (June 2004) : FY05-FY09: 6M$, 6M$, 6M$, 6M$, 6M$. • The Lehman review proposed AIP funding profile for the “Flat-Flat” case (June 2004): FY05-FY09: 6M$, 6M$, 5M$, 4 M$, 3 M$. • The details of these three cases are shown below.

  5. Changes in AIP Work Scope • To get from the Field Task Proposal to the Lehman “Base 2%” case: • One PEP-II RF station was delayed from 2005 to 2006 installation. • The bunch shortening cavities in the HER were eliminated. (Reduces the PEP-II overall peak luminosity from 2.4E34 to about 2.2E34.) • Some PEP-II vacuum work was delayed which delays achievement of the ultimate peak luminosity. • Some non-PEP-II work was delayed.

  6. Further changes in AIP Scope • To get from the Lehman “Base 2%” case to the Lehman “Flat-Flat” case: • Some PEP-II vacuum work was delayed by a year from 2007 to 2008. • Some PEP-II magnet, feedback, and diagnostic work was delayed from 2007 to 2008. • Many non-PEP-II items were delayed. • It is assumed that the early year PEP-II upgrades and people are “protected” except for the above.

  7. AIP Upgrades from SLAC Field Task Proposal April 2004

  8. AIP Upgrades for SLAC Lehman “Base 2%” June 2004

  9. AIP Upgrades for SLAC Lehman “Flat-Flat” June 2004

  10. Integrated PEP-II Luminosity • The PEP-II integrated luminosity for each of the three AIP funding profiles was calculated month by month including the expected down times, turn-on schedules, and anticipated peak luminosities. • The peak luminosity for each year was determined by the available installed hardware. • A listing of the integrated luminosity by year is shown in the table below. • These projections assume that the PEP-II staff for operation, maintenance, engineering, and construction remain at current levels. • In summary: The “Base 2%” case reduces the overall integrated luminosity by about 8% compared to the Field Task Proposal and the “Flat-Flat” case an additional 2%.

  11. PEP-II Delivered Integrated Luminosity under Various Plans

  12. Conclusions • AIP projects have provided the hardware opportunities to successfully increase the luminosity in PEP-II over the past years. • Future AIP project money is important for continued luminosity improvement of PEP-II. • With potential future reductions in the AIP funding, accelerator projects (and the associated luminosity gains) will likely be delayed to later years.

More Related