1 / 7

EDS 3 Release 5 Phase 1 Testing

EDS 3 Release 5 Phase 1 Testing. Monday / Friday Market Updates. September 21, 2007. Agenda. Antitrust Admonition Roll Call Review of Testing Schedule Week’s Plans Common Questions / Reminders / Special Agenda Items Q&A / Open Forum. Antitrust Admonition . ANTITRUST ADMONITION

Audrey
Download Presentation

EDS 3 Release 5 Phase 1 Testing

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EDS 3 Release 5 Phase 1 Testing Monday / Friday Market Updates September 21, 2007 http://nodal.ercot.com 1

  2. Agenda • Antitrust Admonition • Roll Call • Review of Testing Schedule • Week’s Plans • Common Questions / Reminders / Special Agenda Items • Q&A / Open Forum http://nodal.ercot.com 2

  3. Antitrust Admonition ANTITRUST ADMONITION ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws. http://nodal.ercot.com 3

  4. Tests Scheduled for week beginning 9/24 “PING” Test STEC 9/27 **MILESTONE – ALL PING TEST COMPLETE Support / Testing Call Brazos 9/25 Garland 9/25 ANP Funding 9/26 Calpine 9/26 IPA Marketing 9/26 Topaz 9/26 Eagle Energy 9/27 Westar 9/27 Fulcrum 9/28 Scurry Wind 9/28 Tests Scheduled for week beginning 10/01 Support / Testing Call STEC 10/01 **MILESTONE – EDS 3 Phase 1 Complete 2 Week Outlook http://nodal.ercot.com 4

  5. Review of Testing Schedule:Week’s Status Report Note: numbers and percentages include sub-QSE’s http://nodal.ercot.com 5

  6. Common Questions / Reminders / Special Agenda Items • Sandbox Release was Backed Out Due to Issues • New ETA Monday 9/24/2007 • Monday’s Call – Special Agenda Items • Daylight Savings Time • Will be addressed on Monday’s Call • Data Dictionary • Will be addressed on Monday’s Call • Reminders • Continue to have ICCP data sending to ERCOT • Listener Set-Ups /Notifications • Send URL of listener and verify CA to eds3@ercot.com • Request a brief session to test via the eds3@ercot.com • Current only 5 MP’s have their listener up and running and are receiving notifications (6 more are in progress) • EDS Environment will be shut down on Oct 5th for Upgrades • Outage expected to last 1 week • Environment changed, bug fixes, preparations for phase 2 http://nodal.ercot.com 6

  7. Q&A Q&A / Open Forum http://nodal.ercot.com 7

More Related