1 / 6

EDS 3 Release 5 Update

EDS 3 Release 5 Update. Daryl Cote. Clarification to Monday’s Discussion. 6/15. 6/15. 6/22. 6/22. 6/19. 6/19. 7/6. 7/6. 7/13. 7/13. 7/20. 7/20. 7/27. 7/27. 8/3. 8/3. 8/10. 8/10. 8/17. 8/17. 8/24. 8/24. 8/31. 8/31. 9/7. 9/7. 9/14. 9/14. 9/21. 9/21. 9/28. 9/28.

sari
Download Presentation

EDS 3 Release 5 Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EDS 3 Release 5 Update Daryl Cote TPTF Meeting

  2. Clarification to Monday’s Discussion 6/15 6/15 6/22 6/22 6/19 6/19 7/6 7/6 7/13 7/13 7/20 7/20 7/27 7/27 8/3 8/3 8/10 8/10 8/17 8/17 8/24 8/24 8/31 8/31 9/7 9/7 9/14 9/14 9/21 9/21 9/28 9/28 Monday’s illustration was incorrect Planned MMS FAT Complete EIP Dev Start Begin iTEST Migrate & Configure Start EDS3 As Displayed Monday Invalid Delays in Migration & Configuration Actual MMS FAT Complete EIP Dev Start Begin iTEST Start EDS3 Migrate & Configure Planned MMS FAT Complete EIP Dev Start Begin iTEST Migrate & Configure Start EDS3 Correct Illustration Invalid Delays in Migration & Configuration Actual MMS FAT Complete EIP Dev Start Begin iTEST Start EDS3 Migrate & Configure Texas Nodal Program Update

  3. Where are we at Texas Nodal Program Update

  4. How do we get back on schedule • After Development is completed start two parallel efforts • Internal Testing (INT) • Basic functional validation in EDS (EDS) • As defects are found by internal testing and corrected they will be migrated to EDS • After Internal testing is completed, issues submitted by MPs will be reconciled with results from internal testing and acted upon • We have support from three QSEs to take the first support windows Texas Nodal Program Update

  5. Summary of EDS 3 Release 5 SCED Timeline • EDS 3 Release 5 SCED will start on 8/24 • ERCOT is hosting a Kick-off WebEx on 8/1 to review the details • Quality of the software will be non-production grade until internal testing is completed • Issue reported by MPs will be handled after INT testing is complete Texas Nodal Program Update

  6. EDS 3 Release 5 (SCED) Timeline • The EDS team has developed a number of scenarios based on MP input • Working with MMS team to compare FAT Scenarios vs the EDS Scenarios • Will communicate results to TPTF Texas Nodal Program Update

More Related