1. Justification of BCM Projects Implementation approach overview - Decision Methodology: The Key Probability, Cost-Benefit, Intuitive Approaches
4. 1. Estimate Losses by length of outage: Step 2 (Recovery)
5. 2. Determine length of outage by backup/ recovery scenario
6. 3. Perform cost/benefit analysis of each feasible scenario
7. Decision Approaches Probability-based (used in insurance justification)
Analysis-based (used in cost-benefit analysis)
Intuition-based (used by most executives and expert systems)
The analysis-based approach based on fiduciary responsibility will be recommended, since the probability approach and the intuition-based approach can lead to catastrophic loss exposures.
8. Probability-based(used in insurance justification) Mr. probability
Cost of Hot Site Backup $500,000/year
(2% of IS budget)
Direct Losses over ten days $30,000,000
Probability of loss .01/year
Net Direct Loss $300,000/event
ROI -40% (Bad Investment)
9. Another Probability Approach Assume a 30 year life for the Hot Site
Cost of Backup Site over 30 years $15,000,000
Direct Losses over 10 day period $30,000,000
Probability of 1 loss over 30 years 26%
Net Direct Loss $7,800,000
ROI -48% (Bad Investment)
10. Analysis-based(used in Life-Cycle cost-benefit analysis) Mr. Application Analyst
Cost of Backup Site over 30 years $15,000,000
Direct Impact Loss/Event (10 days) $30,000,000
Delayed Loss of Business/Event $360,000,000
(year to recover ˝ sales)
Total $ Loss/Event $390,000,000
(˝ yearly profit)
Probability of Losing our Jobs
and Stockholder Suits 100%