460 likes | 483 Views
AMS Thermal Control System (TCS): A Status Report. Group Leaders: Drj Sun – AIDC, M. Molina – CGS, J. Burger – MIT, J.-R. Tsai – NSPO, L. Cheng – SDU Presented by M. Molina, T.Luan, DrjSun. AMS TCS - main components. TCS Mass budget. Target mass for the TCS = 274 Kg.
E N D
AMS Thermal Control System (TCS): A Status Report Group Leaders: Drj Sun – AIDC, M. Molina – CGS, J. Burger – MIT, J.-R. Tsai – NSPO, L. Cheng – SDU Presented by M. Molina, T.Luan, DrjSun
TCS Mass budget Target mass for the TCS = 274 Kg
Main radiators • They provide the sink to most of the electronic units • The wake one provides the sink to the CAB LHP
Tracker radiators • They provide the sink to the TTCS
Zenith radiators • They provide the sink to the Cryocoolers LHP
Activities since last TIM (Oct 2006) • STA structural analysis • Inserts specimen construction • TWG activities • test review • Thermal analysis • TCS STA Integration • Work with AIDC • Integration Jig • Test coupon design
STA structural analysis • STA will undergo • Static test with 5 load cases • Modal survey test • JS provided CGS/SDU the load cases and a new model of the USS to be used
Max tension force on inserts Main radiator
TENSION TEST 1792 N
Max shear force on inserts Main radiator
SHEAR TEST 5375 N
Max tension force on inserts Tracker radiator
Max shear force on inserts Tracker radiator
Rupture Test Load [Nmm/mm] 34.21 154.61 36.27 27.33 Drum peel test
Rupture Test Load [Kg] 64.61 68.43 54.01 156 65.51 54.21 Flat wise test
Flight loads analysis • When subjected to FM loads inserts will show • Positive margin to tension • Positive margin to shear ONLY with an improved configuration (heavier, i.e. with more glue) • No problem for the STA, because loads are lower • Need of a stronger glue = HOT BONDING
RADIATOR INSERT SPECIMEN TENSION TESTS (Summary Table) CGS Sample Identification Number PLYFORM Sample Identification Number Ultimate Test Load [N] Analysis Limit Load [N] MoS [SF 1.4] Remarks 1 T 06023 ISO1 1841.55 600 600 1.19 2 T 06023 ISO2 1792.78 1.13 3 T 06031 ISO1 2217.25 1.63 4 T 06031 ISO2 2356.70 1.8 5 T 06031 ISO3 2410.88 1.87
RADIATOR INSERT SPECIMEN SHEAR TESTS (Summary Table) CGS Sample Identification Number PLYFORM Sample Identification Number Ultimate Test Load [N] Analysis Limit Load [N] MoS [SF 1.4] Remarks 1 T 06028 ST01 4301.94 3526 -0.12 2 T 06028 ST02 5375.96 3526 -0.088 3 T 06028 ST03 5457.32 3526 -0.1 4 T 06028 ST04 7967.05 3526 0.62 5 T 06028 ST05 6887.25 3526 0.39
Conclusion on inserts testing • A first set of samples has been tested in Italy • OK for the STA • OK for the FM with an improved (heavier) configuration • SOLUTION = Hot bonding process • Cold bonded samples have been sent to NASA for testing and SWG approval • Hot bonded samples will be built and tested by AIDC
Aim of test coupon • Establish and test CGS-AIDC data exchange • Set-up Rohacell sandwich panel technology • Inserts precise positioning • Heat pipes bending and gluing • Skin joining
Inserts • Built by AIDC
Heat pipe • Filled with Ammonia, straight and bent • Profiles only, to be machined at AIDC
Test spec. for the test coupon • Document „AMS-PR-CGS-002“ has been issued and delivered to AIDC • DISTRUCTIVE TESTS ON SPECIMENS • NON DISTRUCTIVE TESTS ON THE TWO TEST COUPONS • Mechanical tests • Thermal tests
Distructive test (1) • The specimens shall be manufactured in according to the following requirements: • Same item materials, coming from the same production lot. • Same surface treatment (according to the Test Coupon Engineering Drawing). • Same item manufacturing procedures. • Same vacuum bag. • Same curing cycle.
Test Type Test Requirement Specimens Quantity INSERT TENSILE ≥ 2350 [N] 15 (TBC) INSERT SHEAR ≥ 7500 [N] 15 (TBC) DRUM PEEL ≥ 5.5 [Nxmm/mm] 5 FLAT-WISE ≥ 610 [N] 5 LAP SHEAR ≥ 37 [N/mm2] 5 Distructive test (2) Reference values
Non-distructive tests • Visual inspection • CMM measurement • Inserts position • Geometrical Tolerances
Thermal test at NSPO • Scope • Determine suitable heat conductance between radiator skin and heat pipes • Details are to be defined by NSPO • Concept: IR Lamp one side, IR camera on the opposite
FM schedule • Integration jig and crate links Jul 2007 • All radiators, brackets and rods Jan 2008 (TBC with AIDC) • Zenith radiator delivery Jun 2008
FM schedule • MLI Mar 2008 • CAB LHP Apr 2008