NE ALBERTA STREET PHASE I Local Improvement District Final Assessment Hearing Bureau of Transportation November 13, 2013. Project is in the Cully Neighborhood and and Provides Important Connectivity Link. Project Petition Support: 100% as Constructed Project Economies of Scale
E N D
NE ALBERTA STREET PHASE I Local Improvement District Final Assessment Hearing Bureau of Transportation November 13, 2013
Project is in the Cully Neighborhood and and Provides Important Connectivity Link
Project Petition Support: 100% as Constructed Project Economies of Scale • Street Length Increased by 11% added NE 78th Ave. • Curb Length Increased by 85% added NE 78th Ave. added NE Alberta St. south side (76th – 79th) • Sidewalk Length Increased by 36% added NE 78th Ave. added NE Alberta St. south side at 78th Actual Project Costs • 14% Less Per Street Centerline Foot than Budgeted