Conference Planning

Conference Planning. What ?  How ? Work Breakdown Structure Estimation of re sources Defin ition of dependencies between planning a c tiviti es Assignment of responsibilities. Work Breakdown Structure (WBS). Proje c t - Hierarchical syst e m ( tree ): Goa l Objectives

abdalla
Download Presentation

Conference Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Conference Planning • What?  How? • Work Breakdown Structure • Estimation of resources • Definition of dependencies betweenplanning activities • Assignmentof responsibilities

  2. Work Breakdown Structure (WBS) • Project - Hierarchical system (tree): • Goal • Objectives • Workpackages • Tasks

  3. Task S.M.A.R.T. Criterion: • Specific • Measurable (costs, work, time) • Assignable (responsibility) • Realistic • Time-related

  4. TASK DESCRIPTION • Task ID, title, description • Input (outcomes of other tasks) • Title,type, description of a deliverable • Start and end time • Effort (e.g. in person-months) • Costs • Responsibility

  5. Example: Conference planning • 1. Conference programme • 1.1 Define programmeof conference • 1.2 Obtain speakers • 1.3 Prepareconference materials • 1.3.1 Obtain presentations fromspeakers • 1.3.2Prepare and print conference materials

  6. Example: Conference planning (2) • 2. Set theconference site & date • 2.1 Set the conference date • 2.2 Select & commit conference site • 2.3 Confirm arrangements

  7. Example: Conference planning (3) • 3. Develop marketingplan • 3.1 Developandprintconference brochure • 3.2 Obtain Label Sets for Direct mailing • 3.3 Mail brochures • 3.4 Receive & acknowledgeregistrations

  8. Duration of a Task • Task duration = Effort / No of persons • Random character Average time of activity duration: TA = (O + 4.M + P) / 6 • O - optimistic completion time • P - pesimistic • M – most likely completion time

  9. COSTS CATEGORIES • Personnel costs • Equipment • Travel and subsistence • Consumables • Other directcosts • Subcontracting • Indirect Costs (overheads)

  10. SEQUENCING THE PROJECT ACTIVITIES • Logical / time dependencies • Types of dependencies: • Finish  Start („Immediate predecessor“) • Start  Finish

  11. Example: Conference planning Activity Title Imm. Pred. A (2.1) Date - B (1.1) Programme - C (2.2) Site A D (1.2) Speakers B E (3.1) Conf.broch. C, D C, D F (3.2) Database

  12. Example: Conference planning(2) Activity Place Imm.Pred. G (3.3) Mailing E, F H (1.3.1) Obtain D I (3.4) Process G J (2.3) Finish H, I K (1.3.2) Print J

  13. Example: Conference Planning A C E G I start F J K end B D H

  14. ASSIGNMENTS • Planning – activity scheduling, assigment team members to tasks • Implementation – realocation of resources • Control – Comparision of plan and current status quo

  15. Summary • Work break down structure (Tasks - S.M.A.R.T.) • Estimation of time and costs (duration, effort, costs) • Sequencing of activities • Project Proposal