1 / 20

FIRE STATION NUMBER 2

FIRE STATION NUMBER 2. Pre-Proposal Conference & Site Visit RFP 2014-014FR April 25, 2014. Project Summary. Goal is to Construct a new, single-story approximately 8,000 Sq. Ft. Fire Station.

abra
Download Presentation

FIRE STATION NUMBER 2

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FIRE STATION NUMBER 2 Pre-Proposal Conference & Site Visit RFP 2014-014FR April 25, 2014

  2. Project Summary • Goal is to Construct a new, single-story approximately 8,000 Sq. Ft. Fire Station. • Alt. Bid item for Demo of existing fire station and providing landscape and irrigation in its place. • City of Palm Beach Gardens – Owner

  3. SITE LOCATION 11025 Campus Drive

  4. EXISTING SITE Front of lot Lot size Approx. 125’ x 840’

  5. Existing Site Conditions

  6. CONCEPTUAL SITE LAYOUT

  7. CONCEPTUAL SITE LAYOUT

  8. Building Requirements • LEED Certified – per state requirements • 72 hours, self-sustained generator (Possible reuse of existing generator as cost saving measure) • Reuse existing 2- convault tanks for fuel island (Diesel and regular - 500 gallons each) • Architecture to match surrounding buildings

  9. Site Requirements • The Existing fire station shall remain open at all times with ingress and egress 24 hours a day. • During construction, all utilities servicing adjacent and off-site facilities shall not be interrupted • Secure staging areas and site at all times with a 6 foot high chain link fence with wind screen • Drainage per SFWMD

  10. Seacoast Utilities Site Site Water & Fire Sewer

  11. Fire Station Program • Site requirements – parking, landscape , etc • Building requirements • Apparatus bay • Watch room • Medical supply room • Officers quarters • Fire fighters bunk rooms – 8 bunks • Restrooms • All requirements are detailed in the Design Criteria Package and included in the schematic drawings and specification book.

  12. Bidding Important Dates • Pre bid meeting & site visit April 25, 2014 • Deadline for questions May 13, 2014 • Bids Due May 16, 2014 • Selection Committee short list May 30, 2014 • Oral Presentations June, 2014 • Project Award Presentation to Council July 10, 2014

  13. Design Phase Design phase of the project will depend on Design-Builder approach to the project and negotiations for award. Owner Assumptions: 120 days for design Typical submittals of 50, 75, 100% City will require Design-Builder to assist in Site plan approval process

  14. Site Plan Approval Process • Designed to Chapter 78 (Land Development Regulations) of the City’s Code • Existing Zoning – Public/Institutional (P/I) • Max lot coverage – 40% • Max build height – 45 ft • A fire station is classified as a Major Conditional Use • Plat will be provided by the City • The site will be a PUD and City will act as agent for site plan approval

  15. Site Plan Approval Process • Required Meetings • Pre-application • DRC • Planning and Zoning meeting • 2 City Council meetings

  16. Pre-Construction Phase Contractor obtains permits (City pays) • Pre-Construction Conference • Construction Schedule • Schedule of Values • Material Submittals • Construction Operations and Safety Plan

  17. Construction Phase • Biweekly Progress Meetings • Confirmation Survey • Zero Safety Mishaps Post-Construction Phase • Punch List • O&M Manuals, Training, Spare Equipment and Finishes • As-Built Drawings (electronic) & velum

  18. Fire Station Number 2 • Budget: $2,600,000 • 425 calendar days to Substantial Completion; 30 calendar days to Final Completion • Liquidated Damages of 0.01% of GMP per day • Optional Items: • Demo of existing fire station, landscape and irrigation of old station

  19. Contact and Due Date • Submit questions and requests for clarification in writing by May : kmra@pbgfl.com • Proposals Due Date: May 16, 2014

  20. RFP2014-014FRDesign Build New Fire Rescue Station No. 2Thank You.

More Related