1 / 47

Acterna Headquarters

This presentation outlines the structural redesign proposal for the Acterna Headquarters in Germantown, Maryland. The existing building is a six-story office building, and the goal is to eliminate intermediate column lines, update to the IBC 2000 code, and create column-free areas.

adenver
Download Presentation

Acterna Headquarters

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Germantown, Maryland Acterna Headquarters John M Sekel The Pennsylvania State University Architectural Engineering 2003 Senior Thesis Presentation Structural Emphasis

  2. Presentation Overview • Existing Building • Proposal • Structural Redesign • Construction Considerations • Architecture Redesign • Mechanical Considerations • Conclusions and recommendations John M Sekel

  3. Existing building • Project Team • Owner: Milestone Industrial, LLC • Architect: Hickok, Warner, Fox Architects • Structural Engineer: Structural Design Group • MEP Engineer: Girard Engineering • General Contractor: L.F. Jennings John M Sekel

  4. Existing Building • General • New corporate campus for Acterna Corporation • Site clearly visible off I-270 outside Washington, D.C. • Six story, 187,500 sf office building • 253’x126’ building footprint • $10 million construction cost • BOCA 1996 design code John M Sekel

  5. Existing Building • Structural • Floor framing • Composite beam and slab construction • 50 ksi wide flange shapes • 30’x25’ typical bays • 3 ¼” lightweight concrete slab on 2” metal decking • 2 – transfer girders over conference room on level 1 • Foundations • Spread footing foundations • 4” first floor slab on grade John M Sekel

  6. Existing Building • Structural • Lateral Frames • 2 – braced frames in each direction John M Sekel

  7. Existing Building • Typical framing plan John M Sekel

  8. Existing Building • Mechanical • VAV boxes with electric duct heaters and reheat coils with VFD • 2 – 15000 cfm VAV A/C units per floor • 2 – 350 ton cooling towers • Plate and frame heat exchanger • Electrical/Lighting • 277/480 volt, 3-phase, 4 wire system • 4000 amp primary switchboard • 2000 amp secondary switchboard • 2’x4’ 277 volt florescent fixtures John M Sekel

  9. Presentation Overview • Existing Building • Proposal • Structural Re-design • Construction Considerations • Architecture Re-design • Mechanical Considerations • Conclusions John M Sekel

  10. Proposal • Structural design goals • Eliminate intermediate column line outside of core • Use long span steel from core to exterior • Economize the structure • Design for ease of construction • Update to IBC 2000 code John M Sekel

  11. Proposal • Architectural design goals • Reflect structural changes in the façade • Open interior spaces, column free areas • Add glazing to lessen “hole-punch” look • Emphasize the drum shape • Predominant architectural feature John M Sekel

  12. Proposal • Construction goals • Reduce construction cost • Reduce construction schedule time • Design building for ease of construction • Mechanical considerations • Analyze impact of façade design on system John M Sekel

  13. Presentation Overview • Existing Building • Proposal • Structural Re-design • Construction Considerations • Architecture Re-design • Mechanical Considerations • Conclusions John M Sekel

  14. Structural depth • Framing Re-design Overview • New bay size outside of core 30’x50’ • 50 ksi wide flange shapes • Most readily available shapes • Possible options • 3 ¼” lightweight concrete slab on 2” metal deck • 2 hour fire rating • Re-size frames for additional gravity load • IBC 2000 lateral loads John M Sekel

  15. Structural depth • Economic steel design measures • Redundant shapes • Simple shear tab connections • Efficient spacing and span direction • Efficient bay size Original 1.5 * 25’ = 37.5’ Redesign 1.5 * 30’ = 45’ Use 50’ to maintain core size John M Sekel

  16. Structural Depth • New framing plan John M Sekel

  17. Structural Depth • New gravity member sizes • Typical Girders • Original: W18 • New Design: W24 • Typical Beams • Original: W14 • New Design: W24 • Typical Interior Column • Original: W12x65 • New Design: W14x120 • Typical Exterior Column • Original: W10x54 • New Design: W14x90 • Deflection criteria controls (L/360) John M Sekel

  18. Structural Depth ƒn calculation 0.18 √[g/(Δg+Δj)] 3.19 Hz • Vibration Analysis • Typical bay analyzed • Wj=157.8 kips • Δj=1.040” • Wg=156.8 kips • Δg’=0.191” • Po=65 lb • β=0.03 • W=157.6 kips ap/g calculation [Po e^(-0.35ƒn)]/βW 0.45%g John M Sekel

  19. Structural Depth • ap/g vs. fn chart • Most accurate between 4 and 8 Hz • Combined mode frequency is 3.19 Hz • Peak acceleration is 0.45% of g • Meets acceptable criteria for office buildings • 0.64% of g at 3.19 Hz John M Sekel

  20. Structural Depth • New Braced Frame Sizes • Original frame layouts and geometries were maintained • Frames 1 & 4: Inverted “V” • Frames 2 & 3: Diagonal • All web members are TS 10”x10”x5/16” • Column sizes increased for higher gravity load • Designed for member strength and drift • Foundations • Spread foundation system • Size and depth increased due to greater load John M Sekel

  21. Presentation Overview • Existing Building • Proposal • Structural Redesign • Construction Considerations • Architecture Redesign • Mechanical Considerations • Conclusions John M Sekel

  22. Construction Breadth • Cost Comparison • RS Means cost estimate for both systems • Cost includes material, labor and equipment John M Sekel

  23. Construction Breadth • Schedule Comparison • Fewer beams to place • Typical floor original: 222 members • Typical floor redesign: 127 members • Fewer columns and foundations • 16 columns removed in redesign • 30% reduction in structure construction time Original Design 20 days foundations 9 weeks superstructure Redesign 14 days foundations 6 ½ weeks superstructure John M Sekel

  24. Presentation Overview • Existing Building • Proposal • Structural Redesign • Construction Considerations • Architecture Redesign • Mechanical Considerations • Conclusions John M Sekel

  25. Architectural Breadth • Reflect change in floor framing Square box-like windows Long, continuous windows John M Sekel

  26. Architectural Breadth • Increase glazing • Emphasize the drum • Vertically spanning glass John M Sekel

  27. Architectural Breadth John M Sekel

  28. Architectural Breadth John M Sekel

  29. Architectural Breadth John M Sekel

  30. Architectural Breadth John M Sekel

  31. Presentation Overview • Existing Building • Proposal • Structural Redesign • Construction Considerations • Architecture Redesign • Mechanical Considerations • Conclusions John M Sekel

  32. Mechanical Breadth • Increase in cooling load • Greater glazing area on facade • Carrier hourly analysis program analysis • Additional 1.5 tons of cooling required per floor • Original system capacity is 92 tons per floor • 1.6% increase • Most likely will not need to resize equipment • Further analysis required John M Sekel

  33. Presentation Overview • Existing Building • Proposal • Structural Redesign • Construction Considerations • Architecture Redesign • Mechanical Considerations • Conclusions John M Sekel

  34. Conclusions • Insignificant cost difference by implementing new system • Shorter construction time • Faster cost return • Improvement to building architecture • Greater tenant flexibility with interior spaces • Good selling point for owner • More notable exterior façade Final Recommendation: Use re-designed structural system John M Sekel

  35. Thank You • Structural Design Group • Mike Weiss • LF Jennings • Kevin Malpass • AE Faculty and staff • Prof. Parfitt, Dr. Geschwinder, Dr. Hanagan • AE classmates • Chris Flynn, Tim Nolan • My parents and roommates for their encouragement and support John M Sekel

  36. Questions? ? ? ? ? ? John M Sekel

  37. Structural Depth • Building Height Comparison John M Sekel

  38. Structural Depth • Plenum heights • 11 ¾” increase per floor • 5’-10 ½” total building height increase John M Sekel

  39. Structural depth • Plenum comparison John M Sekel

  40. Structural Depth • Deflections and camber John M Sekel

  41. Structural Depth • Connections John M Sekel

  42. Structural Depth • Drift John M Sekel

  43. Structural Depth • Drift John M Sekel

  44. Construction Breadth • Working crews • RS Means assumes a steel crew of the following: • (2) Steel foremen • (5) Steel workers • (1) Welder • (1) Welding machine • (1) Oiler operator • (1) Crane operator • (1) 90 ton crane • The daily operating cost for this crew is $4091.40. John M Sekel

  45. Construction Breadth • Crane reach • 60 ton crane • 4 ton pick at 60’ • W21X182 frame column John M Sekel

  46. Construction Breadth • Project delivery system John M Sekel

  47. Construction Breadth • Linear footage comparison • Original structure: 43,300 feet • Redesigned structure: 32,700 feet • Additional cost is hidden in fabrication and materials John M Sekel

More Related