SW 8 th Ave Extension Agreement. Agreement with Town of Tioga, LLC. Total Project: Extension of SW 8 th Ave between SW 122 nd St and SW 143 rd St. Two travel lanes, bike lanes, sidewalk, multiuse path, street trees
E N D
SW 8th Ave Extension Agreement Agreement with Town of Tioga, LLC
Total Project: Extension of SW 8th Ave between SW 122nd St and SW 143rd St. Two travel lanes, bike lanes, sidewalk, multiuse path, street trees This Agreement: Design and Construction of the portion between SW 122nd and SW 133rd Way SW 8th Ave Extension Total Cost Estimate: $6,420,000 Total Estimate for Agreement Portion: $3,700,000 Developer responsible for 9.7% of Cost Remainder reimbursed through SW Impact Fee Fund FDOT CIGP Grant: $2,400,000
Staff Recommendation The Board of County Commissioners approve the agreement with Town of Tioga, LLC to design and construct the SW 8th Avenue extension between SW 122nd St and SW 133rd Way and authorize the Chair's signature.