An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 45th Ave S Shared Street Design Commission September 17th, 2009 Megan Hoyt SDOT Traffic Operations

  2. 2009 Sidewalk Development Program • 25 blocks constructed in 2009 under Bridging the Gap • Standard sidewalk construction (6’ sidewalk, planting strip, curb and gutter) • Prioritization criteria highlights LRT and proximity to services

  3. Project Background • Ranks high in both original and revised (Pedestrian Master Plan) criteria S Cloverdale St Rainier Ave S Dunlap Elementary MLK Jr. Way S 45th Ave S Rainier Beach H.S. South Shore K-8 S HendersonSt Link Light Rail Station Mapes Creek

  4. 45th Ave S details • Zoning is Single Family • Right-of-Way is only 40’ • No existing drainage facilities • RPZ parking zones installed summer 2009

  5. Original Options

  6. Original Options

  7. Public Outreach • Residents of 45th Ave S • Meeting in late May • Significant outreach throughout summer • Seattle Fire Department • Seattle Public Utilities • SDOT Neighborhood Traffic Program

  8. Shared Street Details • 13’ of access maintained • Asphalt paving, established parking stalls, landscaping

  9. Parking space and crosswalk delineation • Stamped asphalt delineates 7’ x 20’ parking space • Stamped colored asphalt crosswalks at entries

  10. Curbless Street – Edge Treatment • Asphalt edge ends at landscaping • Need spot treatment to discourage illegal parking. Options include: • Short concrete curbs • Thickened asphalt edge • Wheelstops

  11. Landscaping • Eight new trees planted • Approx. 3000 SF of new landscaped area • Planting scheme: • Kelsey Dogwood (groundcover) • Geranium (groundcover) • English Lavender • Red flowering Currant • Sword Fern • Orchid Rockrose • Lipstick Strawberry (groundcover)

  12. Timeline • Construction scheduled to begin Sept 28th • Expected completion end of October.