60 likes | 260 Views
Nunn-McCurdy Update. NDIA PMSC Meeting May 21, 2009 Larry Axtell, OUSD(AT&L). Nunn-McCurdy Unit Cost Breaches. “Significant”. “Critical”. Program Acquisition Unit Cost (PAUC) or Average Procurement Unit Cost (APUC) (both in base-year $).
E N D
Nunn-McCurdy Update NDIA PMSC Meeting May 21, 2009 Larry Axtell, OUSD(AT&L)
Nunn-McCurdy Unit Cost Breaches “Significant” “Critical” Program Acquisition Unit Cost (PAUC) or Average Procurement Unit Cost (APUC) (both in base-year $) Current Baseline Estimate +15%+ 25% Original Baseline Estimate +30% +50% Notification Notification, and SAR, and SAR Certification • Compare Current Estimate to Current Baseline Estimate and to Original Baseline Estimate: • Current Estimate – Latest estimate of approved program • Current Baseline Estimate – Currently approved Acquisition Program Baseline (APB) • Original Baseline Estimate – APB approved at MS B or program initiation, whichever is later