PERT / CPM. PERT Program Evaluation & Review Technique CPM Critical Path Method. A Simple Project. Project Network. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Extra Time. Earliest Starting/Finishing Times. EF = ES + t.
E N D
PERT / CPM PERT Program Evaluation & Review Technique CPM Critical Path Method
ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Extra Time
Earliest Starting/Finishing Times EF = ES + t
What if activity times are variable? a optimistic time m most likely time b pessimistic time t = E(T) expected time = (a + 4m + b)/6 V(T) variance = (b - a)2/36
What is the probability that the project takes at least 10 days? • What is the probability that the project takes less than 7 days?