Run II Upgrades Status October 2005 Report & V4.0 Project Plan

Run II Upgrades Status October 2005 Report & V4.0 Project Plan. Pushpa Bhat. Outline. Status Report for October ‘05 % Complete M&S Costs Effort Report Version 4.0 (v4.0) Project Plan Scope Changes v3 vs v4 comparisons Change requests Contingency Analysis. October Status (v3 plan).

ally
Download Presentation

Run II Upgrades Status October 2005 Report & V4.0 Project Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Run II Upgrades Status October 2005 Report& V4.0 Project Plan Pushpa Bhat

  2. Outline • Status Report for October ‘05 • % Complete • M&S Costs • Effort Report • Version 4.0 (v4.0) Project Plan • Scope Changes • v3 vs v4 comparisons • Change requests • Contingency Analysis

  3. October Status (v3 plan) 89% due to shutdown postponement Not re-baselined with new dates With v4, Nov. status ~80% complete,~100% A/P

  4. M&S Spending

  5. Effort Report

  6. Version (v4) PlanScope/Schedule Changes from v3

  7. Upgrade Status in a nutshell • 76% complete as of Oct. 31, 2005, as statused w.r.t. v3.0. • 82 of the 106 A,B,C milestones met • Major tasks : Tev alignment, helix/separators, Tev BPM and many other Tev instrumentation, MI RF upgrade and slip stacking, MI dampers, AP2/DB aperture improvements, AP2 instrumentation, new Li lens, Recycler and e-cool commissioning and integration. • Graduated • Phase-1  Phase 2 with slip-stacking • Phase 2  Phase 3 with e-cool in HEP (defined as in v4) • v3v4: Phase 3, 4 redefined; One major scope deferred (Stacktail bandwidth upgrade); one canceled (TEL3); minor new scopes to be added; new shutdown dates and re-baseline

  8. Redefining Operational Phases • V3: • Phase 2: After slip-stacking  current phase • Phase 3  e-cool for HEP + tank move • Phase 4  bandwidth upgrade +helix • V4: • Phase 3  Integration of e-cool for HEP • Started on October 1, 2005 • Phase 4 : First phase of stacktail upgrade • tank move when we reach stack rates that would require it • Milestone date in v4: 6/13/06 • Defer work on Stacktail bandwidth upgrade • Decision milestone in summer ’06 (mid-July ’06) • back from shutdown in June • Phase 5: bandwidth upgrade and complete remaining pbar aperture +Tev upgrades

  9. Scope/Schedule Changes • MI8 BPM Upgrade • New scope (Cost increase: M&S $98K, Labor: $60K) • Upgrade BPM electronics in MI-8 beamline to help improve performance for slip-stacking operations; new BPMs along with MI8 collimator. (New BPM system similar to new transferline systems under rapid transfers). • Pbar target upgrade • Additional scope • No additional costs; Cost transfer from previously completed tasks on pbar target and beam sweeping • Upgrade pbar target design with improved cooling and motion. Prompted by concerns about target damage in stainless steel and inconel targets in recent operations • Optical Transition Radiation Detectors • Revised scope (No new cost changes) • Detector construction & tests completed. Maybe installed in the Tev this weekend. Installation commissioning to be handed over to Instrumentation Department.

  10. Scope/Schedule Changes • Li Lens • Revised scope, Schedule Changes • Class A milestone Li Lens operational redefined. • Work on prototype-2 was delayed due to change in priorities. Prototype-1 lens (8 mm dia vs 10 mm for PT-2) has been used in operation since 8/1/05 • V4: Li lens operational Class A milestone met 8/15/05 • PT-2 lens to be completed summer ’06 • Fabrication of lenses transferred to the pbar source department after successful evaluation of PT-2. • Accumulator Stacktail system upgrades • Deferred Scope • Stacktail Upgrade: Pause work and include a decision point to proceed or not in mid-July ’06; implement tank move when stack rate/flux warrants it; install full upgrade in ’07 if required  major component for Phase-5.

  11. Scope/Schedule Changes • Pbar Stack Rate Task Force • New Scope (Cost increase: M&S $200K) • Task force under McGinnis for beam-based alignment and aperture improvements throughout the pbar source. For any new diagnostic or instrumentation that might be needed by the task force. • Rapid Transfers (schedule change) • Was tied to shutdown ’05 • Class A Milestone slipped from 10/31/05  2/24/06 • Additional Recycler upgrades • New Scope (Cost increase: M&S $200K, labor $220K) • Upgrades/rebuilding of the power supplies to the Recycler correction elements. The Recycler has lost 8 out of 12 stashes due to failure of the dipole corrector power supplies. The supplies are from the Main Ring and are at least 15 years old.

  12. Scope/Schedule Changes • Additional e-cool System Upgrades • New scope (Cost increase: M&S $165K) • Upgrade Electron Cooling SF6 Gas Recirculation System. The current system was designed for the R&D phase at wide-band Lab. A recent review has concluded that for routine reliable and safe operation, major components of the recirculation system be replaced with an all-in-one skid. • Miscellaneous e-cool upgrades • Chromatic Compensation in Tev lattice • New scope (Cost increase: M&S $150K) • Currently beta-functions for particles with large momentum deviation vary by ~40%. Adversely affects beam-beam effects. Sextupole components will be introduced to correct the chromaticity of beta-function. Important for new working point which will allow more protons. • A review of the project will be held in December.

  13. Scope/Schedule Changes • Tevatron Electron Lens: TEL3 • Reduced Scope (Cost decrease: $340K) • After a review of the status of TEL-2, we have decided to cancel building a third electron lens. TEL-2 tests with new e-gun design and other re-deigned components have been successful. Instead TEL-1 will be modified to be similar to TEL-2. • Cost decrease from canceling TEL3=$600K and costs for upgrading TEL-1~ $260K • IPM • De-scope (No cost implications) • The detector has been built and will likely be installed in the Tevatron next week. The remaining software and commissioning will be handed over to the Tevatron Department.

  14. Reviews • Review Chromatic compensation in the Tevatron • December ‘05 • Review mods to DB Extraction kicker magnet and DB band-4 cooling tanks in Feb. ’06  decision for FY06 shutdown • February ‘06 • Review any newly identified aperture restrictions and make scope decisions • July ’06 • Review Status of Stacktail Bandwidth Upgrade Project • Stack rate • Results from prototype tests if available • July ’06 • Decision point for Bandwidth upgrade in ’07

  15. Change Requests (M&S)

  16. Contingency • V4 Total Estimate:$18098K +$665K = $18763K • Est. to Complete : $18763K - $14469K = $4294K • Available Contingency= total FY04-FY07 budget guidance – Total v4 estimate = $20946K - $18763K = $2283K (53% on estimate to complete) • Contingency held with the Directorate: $2741K before the current CRs

  17. V3 vs v4 Class A Milestones Comparison

  18. V4 Milestones