An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DART Project Update March, 2010

  2. DART - Facts and Background • DART = Donor and Alumni Relationship Tool • Replaces DAC = Donor, Alumni & Constituent system • 2007 RFP – selected Blackbaud • 2008 Fit-Gap to assess Blackbaud Enterprise CRM* (BBEC) • 2009 Funding approved; contract signed • 2010 Working on implementation 2 *CRM = Constituent Relationship Management DART: Donor and Alumni Relationship Tool

  3. Project Organization Overview

  4. DART Project Operating Principles Operating Principles • Broad university-wide engagement (whole community representation) • Focus enterprise-wide on highest impact solutions; prioritize most needed items • Careful review of customizations; be aware of costs and benefits Core Values • Donor- and member-centric in purpose • Productivity is the ultimate goal • Simplicity for the end user • Efficiency in process design • Forward-looking in approach 4 DART: Donor and Alumni Relationship Tool

  5. Timeline Design, data conversion and programming will occur through end of 2010 • 6-months extensive testing, final data verification, system tweaks, training, and unit readiness preparations Go Live scheduled for Summer 2011

  6. DART – Current Activities • Software 1st Round Testing – Constituent functional area (Includes donor/alumni biographical data, relationships, organizational data, and other basic data) • Sprints(Blackbaud programming) – Revenue functional area (Includes gift processing, reporting & lifecycle of the gift) • DesignTeams Underway – Annual Giving, Campaign, & Prospect Research • Design Coming Up – April - Prospect Management, Stewardship and Planned Giving in April; June – Events, more Online Community in June • Data mapping/conversion – Constituent, Revenue data • Developing System Interfaces – Revenue 6 DART: Donor and Alumni Relationship Tool

  7. Keeping Informed / Providing Input Input opportunities • Product Demos • E-mail a question to DART-FAQ@umich.edu DART Project Web Site http://tinyurl.com/DARTproject 7 DART: Donor and Alumni Relationship Tool

  8. DART Demonstration • Guided tour of Blackbaud’s base product. • Design teams are working with Blackbaud to configure this base product for U-M’s needs. • This 15 minute recording (by Karen Isble and Peg Lutz) is divided into three short segments. • Launch the recorded demonstrationhttp://tinyurl.com/DARTdemo1 • For optimal viewing, configure your display settings to 1152 X 864.

More Related