Status Day-Ahead Load Response Program. Presented: Demand Response Working Group August 4, 2004. July 13 – Markets Committee. Presented DALRP Provided estimated pay-back on development costs ISO agreed to review program design if 50 MW clears in an hour
E N D
Status Day-Ahead Load Response Program Presented: Demand Response Working Group August 4, 2004
July 13 – Markets Committee • Presented DALRP • Provided estimated pay-back on development costs • ISO agreed to review program design • if 50 MW clears in an hour • Consult with MC in review of program design • Received 60% in favor • Cost allocation still an issue
August 6 – Participants Committee • ISO is bringing DALRP to NPC for a vote • ISO has included all changes we accepted at the MC • Material included in “Supplemental Notice” to NPC